AIRLINK 58.23 Decreased By ▼ -0.37 (-0.63%)
BOP 6.24 Increased By ▲ 0.03 (0.48%)
CNERGY 3.97 Decreased By ▼ -0.02 (-0.5%)
DFML 16.07 Increased By ▲ 0.06 (0.37%)
DGKC 67.61 Increased By ▲ 0.29 (0.43%)
FCCL 17.82 Increased By ▲ 0.27 (1.54%)
FFBL 25.40 Decreased By ▼ -0.49 (-1.89%)
FFL 9.15 Increased By ▲ 0.01 (0.11%)
GGL 9.79 Increased By ▲ 0.02 (0.2%)
HBL 113.77 Increased By ▲ 1.27 (1.13%)
HUBC 111.61 Decreased By ▼ -3.68 (-3.19%)
HUMNL 6.55 Decreased By ▼ -0.04 (-0.61%)
KEL 4.39 Increased By ▲ 0.17 (4.03%)
KOSM 4.59 Increased By ▲ 1.03 (28.93%)
MLCF 37.73 Increased By ▲ 0.62 (1.67%)
OGDC 125.21 Increased By ▲ 8.81 (7.57%)
PAEL 22.61 Decreased By ▼ -0.10 (-0.44%)
PIAA 11.10 Increased By ▲ 0.31 (2.87%)
PIBTL 6.17 Decreased By ▼ -0.08 (-1.28%)
PPL 109.07 Increased By ▲ 5.07 (4.88%)
PRL 26.84 Increased By ▲ 0.45 (1.71%)
PTC 10.48 Increased By ▲ 0.95 (9.97%)
SEARL 52.85 Increased By ▲ 0.86 (1.65%)
SNGP 66.38 Increased By ▲ 1.26 (1.93%)
SSGC 11.01 Increased By ▲ 0.08 (0.73%)
TELE 7.13 Decreased By ▼ -0.08 (-1.11%)
TPLP 11.93 Decreased By ▼ -0.06 (-0.5%)
TRG 76.07 Decreased By ▼ -0.78 (-1.01%)
UNITY 20.47 Decreased By ▼ -0.02 (-0.1%)
WTL 1.30 No Change ▼ 0.00 (0%)
BR100 6,441 Increased By 109.2 (1.72%)
BR30 22,098 Increased By 468.8 (2.17%)
KSE100 62,816 Increased By 901.5 (1.46%)
KSE30 21,134 Increased By 282.7 (1.36%)
Pakistan

Human error caused countrywide blackout on Jan 9, reveals inquiry committee report

  • Report states that the fault occurred as some officials did not follow SOPs during maintenance work
  • Last month, country plunged into darkness after the National Transmission and Despatch Company power system encountered a major breakdown due to the tripping of the Guddu Thermal Power Plant
Published February 23, 2021

(Karachi) An inquiry committee, tasked to investigate countrywide blackout on January 9, has held officials of Guddu Thermal Power Plant responsible, local media reported on Tuesday.

As per details, the Power Division informed a parliamentary panel about the findings. Secretary Power Ali Raza Bhutta briefed the members of the National Assembly Standing Committee on Energy.

Bhutta said, “The problem occurred due to a human error at the Guddu power station. The error led to the tripping of the entire power system. The fault occurred as some officials did not follow SOPs during maintenance work.”

“Due to a mistake, the Guddu Thermal Power Plant tripped and there was a complete blackout. At the time of the blackout, the power consumption in the country stood at 10,000 megawatts,” he added.

Last month, country plunged into darkness after the National Transmission and Despatch Company (NTDC) power system encountered a major breakdown due to the tripping of the Guddu Thermal Power Plant at around midnight.

The blackout also partially disrupted the telecommunication system in the country and people from different cities and towns reported a massive drop in mobile phone signals. Initial reports had suggested that Guddu Thermal Power Plant’s power system developed a technical fault.

Soon after the blackout, Federal Minister for Power Omar Ayub Khan posted a twitter message, saying: "Tripping of high transmission line nationwide has brought down the system frequency from 50 to zero in less than one second. The drop in infrequency caused tripping of power stations nationwide."

Later, the NTDC constituted a four-member committee to probe into the reasons and facts leading to collapse of the power system and determine the responsibility. The committee was also to suggest measures to prevent occurrence of such incidents in future in 7 days.

In view of a preliminary inquiry, the Central Power Generation Company had also suspended seven of its employees working under Plant Manager-III for alleged negligence.