BML 5.03 Increased By ▲ 0.02 (0.4%)
BOP 12.92 Decreased By ▼ -0.16 (-1.22%)
CNERGY 7.18 Increased By ▲ 0.06 (0.84%)
CPHL 88.15 Increased By ▲ 0.70 (0.8%)
DCL 14.65 Increased By ▲ 0.31 (2.16%)
DGKC 172.10 Increased By ▲ 1.34 (0.78%)
FCCL 47.00 Increased By ▲ 0.24 (0.51%)
FFL 16.09 Increased By ▲ 0.27 (1.71%)
GCIL 26.90 Increased By ▲ 0.03 (0.11%)
HUBC 147.66 Increased By ▲ 3.48 (2.41%)
KEL 5.16 Increased By ▲ 0.09 (1.78%)
KOSM 6.64 Decreased By ▼ -0.05 (-0.75%)
LOTCHEM 20.74 Increased By ▲ 0.15 (0.73%)
MLCF 85.65 Increased By ▲ 0.92 (1.09%)
NBP 122.40 Increased By ▲ 0.58 (0.48%)
PAEL 43.88 Increased By ▲ 0.42 (0.97%)
PIAHCLA 22.30 Increased By ▲ 0.01 (0.04%)
PIBTL 9.00 Increased By ▲ 0.07 (0.78%)
POWER 14.16 Increased By ▲ 0.15 (1.07%)
PPL 170.49 Increased By ▲ 0.55 (0.32%)
PREMA 43.05 Decreased By ▼ -0.34 (-0.78%)
PRL 33.26 Increased By ▲ 0.15 (0.45%)
PTC 24.12 Decreased By ▼ -0.14 (-0.58%)
SNGP 119.49 Decreased By ▼ -0.15 (-0.13%)
SSGC 46.34 Increased By ▲ 0.79 (1.73%)
TELE 8.13 Increased By ▲ 0.05 (0.62%)
TPLP 10.45 Decreased By ▼ -0.02 (-0.19%)
TREET 24.09 Increased By ▲ 0.12 (0.5%)
TRG 57.90 Decreased By ▼ -0.15 (-0.26%)
WTL 1.54 Increased By ▲ 0.02 (1.32%)
BR100 13,742 Increased By 111.4 (0.82%)
BR30 40,190 Increased By 339.1 (0.85%)
KSE100 135,433 Increased By 1133.1 (0.84%)
KSE30 41,166 Increased By 352 (0.86%)

ISLAMABAD: The World Bank (WB) has rated the overall implementation progress of Punjab Human Capital Investment Project (PHCIP) worth $200 million moderately unsatisfactory.

The Project Development Objective (PDO) was to increase the utilisation of quality health services, and economic and social inclusion programmes, among poor and vulnerable households in select districts in Punjab.

However, progress towards achievement of PDO, as well as overall implementation progress is moderately unsatisfactory, official documents of the bank revealed.

Social protection: World Bank’s $200m Punjab project makes little progress

Documents further stated that despite initial delays owing to repeated COVID lockdowns since the project’s effectiveness in May 2020, an encouraging turnaround is noted from the beginning of 2023.

In the last six months, the government of Punjab took key decisions in streamlining the Project’s governance and decision making structure, coupled with rigorous follow up on project’s physical and financial targets.

A revised Project PC-1 has been approved, and important procurements, such as hiring of the Enterprise Resource Planning (ERP) firm have been completed.

The contract with OR firm is also operationalised, and the firm has begun work in the field. Additional key procurements are also at an advanced stage. Under the health component, 140 regular Basic Health Units (BHUs) were upgraded to 24/7 BHUs; 100 per cent of 24/7 BHUs have implemented electronic medical records (EMR); and 5,229,012 people were provided with essential health, nutrition, and population (HNP) services. 93 per cent of CCT beneficiary women were satisfied with health services provided.

Under the social protection component, beneficiary enrolment of CCT has increased to 229,580, and the upgradation of payment system has significantly improved the number of beneficiaries accounts opened and subsequent cash disbursement.

Under the economic inclusion component, 51,960 households have been enrolled, and assets have been transferred to over 24,000 beneficiaries.

Under the education component, minor civil works have been completed at all 3,400 project schools and delivery of age-appropriate furniture has begun.

Key activities requiring expeditious actions and regular monitoring include: priority implementation of social mobilisation; rollout of updated payment service provider SOPs; roll out of economic inclusion package-3 to the remaining project beneficiaries; and swift completion of pipeline procurements related to school furniture, books, and healthcare equipment.

Copyright Business Recorder, 2023