AIRLINK 74.00 Decreased By ▼ -0.25 (-0.34%)
BOP 5.14 Increased By ▲ 0.09 (1.78%)
CNERGY 4.55 Increased By ▲ 0.13 (2.94%)
DFML 37.15 Increased By ▲ 1.31 (3.66%)
DGKC 89.90 Increased By ▲ 1.90 (2.16%)
FCCL 22.40 Increased By ▲ 0.20 (0.9%)
FFBL 33.03 Increased By ▲ 0.31 (0.95%)
FFL 9.75 Decreased By ▼ -0.04 (-0.41%)
GGL 10.75 Decreased By ▼ -0.05 (-0.46%)
HBL 115.50 Decreased By ▼ -0.40 (-0.35%)
HUBC 137.10 Increased By ▲ 1.26 (0.93%)
HUMNL 9.95 Increased By ▲ 0.11 (1.12%)
KEL 4.60 Decreased By ▼ -0.01 (-0.22%)
KOSM 4.83 Increased By ▲ 0.17 (3.65%)
MLCF 39.75 Decreased By ▼ -0.13 (-0.33%)
OGDC 138.20 Increased By ▲ 0.30 (0.22%)
PAEL 27.00 Increased By ▲ 0.57 (2.16%)
PIAA 24.24 Decreased By ▼ -2.04 (-7.76%)
PIBTL 6.74 Decreased By ▼ -0.02 (-0.3%)
PPL 123.62 Increased By ▲ 0.72 (0.59%)
PRL 27.40 Increased By ▲ 0.71 (2.66%)
PTC 13.90 Decreased By ▼ -0.10 (-0.71%)
SEARL 61.75 Increased By ▲ 3.05 (5.2%)
SNGP 70.15 Decreased By ▼ -0.25 (-0.36%)
SSGC 10.52 Increased By ▲ 0.16 (1.54%)
TELE 8.57 Increased By ▲ 0.01 (0.12%)
TPLP 11.10 Decreased By ▼ -0.28 (-2.46%)
TRG 64.02 Decreased By ▼ -0.21 (-0.33%)
UNITY 26.76 Increased By ▲ 0.71 (2.73%)
WTL 1.38 No Change ▼ 0.00 (0%)
BR100 7,874 Increased By 36.2 (0.46%)
BR30 25,596 Increased By 136 (0.53%)
KSE100 75,342 Increased By 411.7 (0.55%)
KSE30 24,214 Increased By 68.6 (0.28%)
Pakistan

Orange Line project full of red flags

Due to multitudes of issues and several delays, the project completion was delayed by a year and with over Rs.169 b
Published February 24, 2020 Updated February 25, 2020
  • Due to multitudes of issues and several delays, the project completion was delayed by a year and with over Rs.169 billion spent, the government is looking to begin operations to start revenue generation.
  • Experts from LESCO state that daily electricity consumption will total to an estimated 25 million which amounts to a cost of 750 million rupees per month that the government will have to incur to run the project.

It is no secret that the Orange Line project was doomed from the start. The ambitious project was and still is unsustainable for an ailing economy like Pakistan. Yet, the previous government has spent such a significant amount on the project that the Orange Line metro is stuck.

Due to multitudes of issues and several delays, the project completion was delayed by a year and with over Rs.169 billion spent, the government is looking to begin operations to start revenue generation. Yet, reports from the Lahore Electric Supply Company (LESCO) stated that during the 90-hour test run conducted earlier, 2.7 million electricity units were consumed. In Rupees, that comes out to approximately 50 million.

Experts from LESCO state that daily electricity consumption will total to an estimated 25million which amounts to a cost of 750million rupees per month that the government will have to incur to run the project. Questions arise on how feasibility studies and risk assessments recommended to approve the project that runs along 27kms of track in Lahore.

Ticket prices are set to be capped at Rs.60, which would require a Rs. 10 billion subsidy to operate the metro line. CM Punjab went on record to state that to break even, a ticket would need to be charged at Rs. 285 and that there are much better uses of subsidies than to fund a 27km track.

While the project is a Belt and Road Initiative collaboration, the government must seriously assess the red flags that loom over the Orange line. To continue the nightmare of the Rs. 200billion spent (read: wasted) and continue to hinder the ailing economy, or have your hat-in-hand and shut down a project that should never have been commissioned?