AGL 5.27 Decreased By ▼ -0.13 (-2.41%)
ANL 8.75 Decreased By ▼ -0.04 (-0.46%)
AVN 76.62 Increased By ▲ 0.37 (0.49%)
BOP 5.22 Increased By ▲ 0.03 (0.58%)
CNERGY 4.44 Decreased By ▼ -0.04 (-0.89%)
EFERT 81.32 Increased By ▲ 0.22 (0.27%)
EPCL 49.39 Increased By ▲ 0.38 (0.78%)
FCCL 12.80 Increased By ▲ 0.10 (0.79%)
FFL 5.59 Decreased By ▼ -0.03 (-0.53%)
FLYNG 6.90 Decreased By ▼ -0.03 (-0.43%)
FNEL 4.67 Increased By ▲ 0.02 (0.43%)
GGGL 8.64 Increased By ▲ 0.04 (0.47%)
GGL 14.21 Increased By ▲ 0.06 (0.42%)
HUMNL 5.54 Increased By ▲ 0.05 (0.91%)
KEL 2.63 Increased By ▲ 0.04 (1.54%)
LOTCHEM 28.04 Increased By ▲ 0.33 (1.19%)
MLCF 24.05 Increased By ▲ 0.45 (1.91%)
OGDC 71.13 Decreased By ▼ -0.44 (-0.61%)
PAEL 15.34 Increased By ▲ 0.14 (0.92%)
PIBTL 4.87 Decreased By ▼ -0.04 (-0.81%)
PRL 16.08 Increased By ▲ 0.25 (1.58%)
SILK 1.13 Increased By ▲ 0.08 (7.62%)
TELE 9.07 Increased By ▲ 0.08 (0.89%)
TPL 7.09 Decreased By ▼ -0.07 (-0.98%)
TPLP 19.09 Decreased By ▼ -0.09 (-0.47%)
TREET 21.20 Increased By ▲ 0.06 (0.28%)
TRG 139.80 Increased By ▲ 3.30 (2.42%)
UNITY 16.77 Increased By ▲ 0.01 (0.06%)
WAVES 9.41 Increased By ▲ 0.26 (2.84%)
WTL 1.36 Decreased By ▼ -0.02 (-1.45%)
BR100 4,186 Increased By 30.5 (0.73%)
BR30 15,467 Increased By 131.3 (0.86%)
KSE100 41,819 Increased By 279.4 (0.67%)
KSE30 15,448 Increased By 82.9 (0.54%)
Follow us

KARACHI: A landmark achievement has been accomplished at Jagran - II HPP where FWO devised a strategy to excavate the upstream with downstream portions of the Main Headrace Tunnel by carrying out excavation from both ends in opposite directions and meeting in the middle. This happened on 27th January 2021 when the milestone of meeting the two tunnels with a tolerance of less than 10 centimetres, was achieved successfully - this has never been done before in Pakistan.

FWO, while maintaining its professional integrity and credibility, has excavated 1.88 kilometres of Main Headrace Tunnel without even a single casualty in just 215 working days. Currently, FWO has completed 3.7 kilometres of tunnels excavation (including 2.9 kilometre of main headrace tunnel). Multiple construction teams of FWO are working round the clock on Weir, Underground Desander, Tunnels/ Pressure Shafts and Powerhouse.

Jaggran – II HPP is one of the main hydel projects on Jagran River Energy Corridor. It is being financed by Power Development Organization AJK & constructed by FWO in joint venture with HMC-CNTIC-BITC. This project once completed, will add 48MW electricity to the national grid.—PR

Copyright Business Recorder, 2021

FWO

Comments

Comments are closed.

Jagran - II HPP: FWO achieves milestone of meeting two tunnels successfully

Schools in Lahore to remain closed three days a week due to smog

Rupee registers marginal decline, settles at 224.16 against US dollar

ECP supports use of electronic voting machines: Chief Election Commissioner

Business Confidence Score lowest in Pakistan since Covid: OICCI survey

Energy-efficient projects: World Bank ready to extend $300m financing

Battered Pakistan seek livelier pitch in 2nd Test against England

Oil from Russia: Musadik says there will be no US sanctions

IMF programme: Govt remains committed, Dar tells Nong

Poor countries’ debt servicing costliest: World Bank

ECC asks Power Division to resolve KE issues