AGL 38.78 Decreased By ▼ -0.72 (-1.82%)
AIRLINK 194.29 Increased By ▲ 17.66 (10%)
BOP 10.84 Increased By ▲ 0.75 (7.43%)
CNERGY 6.87 No Change ▼ 0.00 (0%)
DCL 10.19 Increased By ▲ 0.26 (2.62%)
DFML 43.13 Increased By ▲ 0.39 (0.91%)
DGKC 96.61 Decreased By ▼ -1.56 (-1.59%)
FCCL 38.07 Decreased By ▼ -1.24 (-3.15%)
FFBL 81.43 Decreased By ▼ -0.43 (-0.53%)
FFL 14.03 Decreased By ▼ -0.36 (-2.5%)
HUBC 118.98 Decreased By ▼ -2.46 (-2.03%)
HUMNL 14.77 Decreased By ▼ -0.57 (-3.72%)
KEL 5.74 Increased By ▲ 0.08 (1.41%)
KOSM 8.49 Increased By ▲ 0.37 (4.56%)
MLCF 46.54 Decreased By ▼ -1.57 (-3.26%)
NBP 77.23 Increased By ▲ 1.41 (1.86%)
OGDC 194.78 Decreased By ▼ -2.63 (-1.33%)
PAEL 34.74 Increased By ▲ 2.36 (7.29%)
PIBTL 8.38 Increased By ▲ 0.23 (2.82%)
PPL 174.57 Decreased By ▼ -0.93 (-0.53%)
PRL 33.17 Decreased By ▼ -0.92 (-2.7%)
PTC 24.57 Increased By ▲ 2.23 (9.98%)
SEARL 110.04 Increased By ▲ 6.84 (6.63%)
TELE 8.90 Increased By ▲ 0.39 (4.58%)
TOMCL 34.83 Decreased By ▼ -0.20 (-0.57%)
TPLP 11.69 Increased By ▲ 0.43 (3.82%)
TREET 18.56 Decreased By ▼ -0.59 (-3.08%)
TRG 60.06 Increased By ▲ 1.50 (2.56%)
UNITY 36.49 Increased By ▲ 1.63 (4.68%)
WTL 1.75 Increased By ▲ 0.16 (10.06%)
BR100 11,701 Increased By 49.8 (0.43%)
BR30 35,411 Decreased By -67.2 (-0.19%)
KSE100 109,054 Increased By 815 (0.75%)
KSE30 33,849 Increased By 155.6 (0.46%)

LAHORE: Chairman Wapda Engr Lt Gen Sajjad Ghani (r) visited under-construction 1530 MW-Tarbela 5th Extension and reviewed the progress on the project.

The Chairman had a detailed visit of the key sites, which include the raised intake, the tunnel and the power house, and witnessed the construction work. During the on-site briefing, the Project Director and the Construction Manager briefed the Chairman about the milestone achieved on these sites.

Temporary support work in the tunnel is complete paving the way for commencement of construction on the connecting tunnel. Installation of equipment such as draft tubes of all three units - Unit No 18, 19 and 20 - is in progress at the power house site. While, the Contractor is all set to resume construction work on the raised intake structure once the water in the reservoir recedes to the required level.

Following the site visit, the Chairman presided over a meeting at the project office attended by the GM Tarbela Dam, PD T5, the Consultants and the Contractors. Overall progress on the project was discussed during the meeting.

It was briefed that construction is continuing on all six work fronts simultaneously. The project is likely to be completed in 2025-26. Thorough deliberations were also made on the work plan for meeting the timelines. The Chairman was of the view that concerted efforts are needed on part of the Consultants and the Contractor to complete the project as per the schedule. Deployment of additional resources is also inevitable for the purpose, he said.

Tarbela 5th Extension Hydropower Project is a component of green, clean and least-cost energy generation plan of Wapda. World Bank and Asian Infrastructure Investment Bank are providing financial assistance for the project to the tune of $390 million and $300 million respectively.