AIRLINK 74.00 Decreased By ▼ -0.25 (-0.34%)
BOP 5.14 Increased By ▲ 0.09 (1.78%)
CNERGY 4.55 Increased By ▲ 0.13 (2.94%)
DFML 37.15 Increased By ▲ 1.31 (3.66%)
DGKC 89.90 Increased By ▲ 1.90 (2.16%)
FCCL 22.40 Increased By ▲ 0.20 (0.9%)
FFBL 33.03 Increased By ▲ 0.31 (0.95%)
FFL 9.75 Decreased By ▼ -0.04 (-0.41%)
GGL 10.75 Decreased By ▼ -0.05 (-0.46%)
HBL 115.50 Decreased By ▼ -0.40 (-0.35%)
HUBC 137.10 Increased By ▲ 1.26 (0.93%)
HUMNL 9.95 Increased By ▲ 0.11 (1.12%)
KEL 4.60 Decreased By ▼ -0.01 (-0.22%)
KOSM 4.83 Increased By ▲ 0.17 (3.65%)
MLCF 39.75 Decreased By ▼ -0.13 (-0.33%)
OGDC 138.20 Increased By ▲ 0.30 (0.22%)
PAEL 27.00 Increased By ▲ 0.57 (2.16%)
PIAA 24.24 Decreased By ▼ -2.04 (-7.76%)
PIBTL 6.74 Decreased By ▼ -0.02 (-0.3%)
PPL 123.62 Increased By ▲ 0.72 (0.59%)
PRL 27.40 Increased By ▲ 0.71 (2.66%)
PTC 13.90 Decreased By ▼ -0.10 (-0.71%)
SEARL 61.75 Increased By ▲ 3.05 (5.2%)
SNGP 70.15 Decreased By ▼ -0.25 (-0.36%)
SSGC 10.52 Increased By ▲ 0.16 (1.54%)
TELE 8.57 Increased By ▲ 0.01 (0.12%)
TPLP 11.10 Decreased By ▼ -0.28 (-2.46%)
TRG 64.02 Decreased By ▼ -0.21 (-0.33%)
UNITY 26.76 Increased By ▲ 0.71 (2.73%)
WTL 1.38 No Change ▼ 0.00 (0%)
BR100 7,874 Increased By 36.2 (0.46%)
BR30 25,596 Increased By 136 (0.53%)
KSE100 75,342 Increased By 411.7 (0.55%)
KSE30 24,214 Increased By 68.6 (0.28%)
Pakistan

Rs2.2bn approved for Chitral Hydel Power Station's capacity enhancement

ISLAMABAD: The government has approved a project worth Rs 2.
Published November 23, 2016

imageISLAMABAD: The government has approved a project worth Rs 2.2 billion to enhance capacity of Chitral Hydel Power Station from one Megawatt to five megawatt.

The capacity enhancement project had been approved by the Central Development Working Party (CDWP) in its recently held meeting, official sources in the ministry of planning, development and reforms here on Wednesday said.

The PC-I of the project had been submitted to the Ministry of Water and Power after the power demand in Chitral area increased and there was a dire need to upgrade the capacity of existing Hydel Power Station at Chitral.

The concept paper of the project was forwarded to Ministry of Planning, Development and Reforms on November 11, 2014 for approval.

The existing 1.0 MW Chitral Hydel Power Station was located on the right bank of Lutkho River, 5 Km upstream of Chitral City.

The Project was commissioned in 1975 by diverting the flows of Lutkho River through 3.72 Km long channel and installing two units of 200 KW and two units of 300 KW each.

The power generated from Chitral Hydel Power Station was supplied to Chitral City through 11 KV Transmission Line.

In the initial construction phase of Project, limited flows of Lutkho River were diverted to Power Channel for generation of 1 MW only.

However the river had abundant flows which could be utilized for Power Generation by constructing a small diversion weir, remodeling of power channel and fore bay and installation of new penstocks and additional units. It was estimated that the power could be enhanced up to five MW.

WAPDA had preliminary studies for the proposed up-gradation. Topographic Survey, Geological Mapping for weir Intake, Power Channel and Power House areas and drilling at weir and Power House area were carried out. Tender Design Report had been completed by Hydro Planning WAPDA in May, 2012.

The estimated cost of the project was US$ 15 million and completion time was three years.

Copyright APP (Associated Press of Pakistan), 2016