AIRLINK 79.30 Decreased By ▼ -0.11 (-0.14%)
BOP 5.31 Decreased By ▼ -0.02 (-0.38%)
CNERGY 4.37 Decreased By ▼ -0.01 (-0.23%)
DFML 33.65 Increased By ▲ 0.46 (1.39%)
DGKC 76.00 Decreased By ▼ -0.87 (-1.13%)
FCCL 20.40 Decreased By ▼ -0.13 (-0.63%)
FFBL 31.48 Increased By ▲ 0.08 (0.25%)
FFL 9.84 Decreased By ▼ -0.01 (-0.1%)
GGL 10.23 Decreased By ▼ -0.02 (-0.2%)
HBL 116.75 Decreased By ▼ -1.18 (-1%)
HUBC 134.23 Increased By ▲ 0.13 (0.1%)
HUMNL 7.00 No Change ▼ 0.00 (0%)
KEL 4.58 Decreased By ▼ -0.09 (-1.93%)
KOSM 4.63 Decreased By ▼ -0.11 (-2.32%)
MLCF 37.18 Decreased By ▼ -0.26 (-0.69%)
OGDC 136.50 Decreased By ▼ -0.20 (-0.15%)
PAEL 23.05 Decreased By ▼ -0.10 (-0.43%)
PIAA 27.24 Increased By ▲ 0.69 (2.6%)
PIBTL 6.92 Decreased By ▼ -0.08 (-1.14%)
PPL 113.75 No Change ▼ 0.00 (0%)
PRL 27.39 Decreased By ▼ -0.13 (-0.47%)
PTC 14.92 Increased By ▲ 0.17 (1.15%)
SEARL 57.16 Decreased By ▼ -0.04 (-0.07%)
SNGP 66.81 Decreased By ▼ -0.69 (-1.02%)
SSGC 11.00 Decreased By ▼ -0.09 (-0.81%)
TELE 9.26 Increased By ▲ 0.03 (0.33%)
TPLP 11.65 Increased By ▲ 0.09 (0.78%)
TRG 72.00 Decreased By ▼ -0.10 (-0.14%)
UNITY 25.25 Increased By ▲ 0.43 (1.73%)
WTL 1.40 No Change ▼ 0.00 (0%)
BR100 7,519 Decreased By -6.6 (-0.09%)
BR30 24,579 Decreased By -71 (-0.29%)
KSE100 71,889 Decreased By -82.1 (-0.11%)
KSE30 23,731 Decreased By -17.8 (-0.08%)
Pakistan

97.5pc work on Neelum Jhelum hydropower project completed

ISLAMABAD: As many as overall 97.5 per cent work has already been completed on the strategically important 969 MW Ne
Published 08 Feb, 2018 12:00am

ISLAMABAD: As many as overall 97.5 per cent work has already been completed on the strategically important 969 MW Neelum Jhelum Hydropower Project and its wet testing will be carried out in March.

This was stated by Neelum-Jhelum Hydropower Project Chief Executive Officer Brig (R) Muhammad Zareen while taking to APP.

He said 100 per cent concrete work of the project had already been completed besides 98 per cent dry test of the equipments.

The CEO said that National Transmission and Despatch Company (NTDC) would hand over 500 kV transmission line on February 11-12 after which feed back of switch- yard would be assessed.

Muhammad Zareen said that water filling (pressurization) of its water way system comprising 51.5-kilometer long tunnels has also been commenced in January.

He said the project was fast heading towards completion and most of the works – critical in nature – had been successfully completed.

Construction of the weir (dam) of the project, water way system, installation of electrical and mechanical equipments including turbines, generators and transformers in the power house and the switch-yard and dry-testing of these equipments had already been completed, he said.

Neelum Jhelum Hydropower Project is being constructed on river Neelum in Azad Jammu and Kashmir. The project is an engineering marvel with 90 percent of the project being underground in the high mountain areas.

It is worth mentioning that Neelum Jhelum Hydropower Project is a component of least-cost energy generation plan, being implemented by WAPDA on priority.

It has four generating units, each of them having a capacity of 242.25 MW. The first unit will start electricity generation in March this year, followed by the second third and fourth units at one month interval respectively.

The project will provide about five billion of low-cost and environment-friendly electricity to the national grid every year. Annual benefits of the project have been estimated at Rs 50 billion.