AIRLINK 73.06 Decreased By ▼ -6.94 (-8.68%)
BOP 5.09 Decreased By ▼ -0.09 (-1.74%)
CNERGY 4.37 Decreased By ▼ -0.09 (-2.02%)
DFML 32.45 Decreased By ▼ -2.71 (-7.71%)
DGKC 75.49 Decreased By ▼ -1.39 (-1.81%)
FCCL 19.52 Decreased By ▼ -0.46 (-2.3%)
FFBL 36.15 Increased By ▲ 0.55 (1.54%)
FFL 9.22 Decreased By ▼ -0.31 (-3.25%)
GGL 9.85 Decreased By ▼ -0.31 (-3.05%)
HBL 116.70 Decreased By ▼ -0.30 (-0.26%)
HUBC 132.69 Increased By ▲ 0.19 (0.14%)
HUMNL 7.10 Increased By ▲ 0.04 (0.57%)
KEL 4.41 Decreased By ▼ -0.24 (-5.16%)
KOSM 4.40 Decreased By ▼ -0.25 (-5.38%)
MLCF 36.20 Decreased By ▼ -1.30 (-3.47%)
OGDC 133.50 Decreased By ▼ -0.97 (-0.72%)
PAEL 22.60 Decreased By ▼ -0.30 (-1.31%)
PIAA 26.01 Decreased By ▼ -0.62 (-2.33%)
PIBTL 6.55 Decreased By ▼ -0.26 (-3.82%)
PPL 115.31 Increased By ▲ 3.21 (2.86%)
PRL 26.63 Decreased By ▼ -0.57 (-2.1%)
PTC 14.10 Decreased By ▼ -0.28 (-1.95%)
SEARL 53.45 Decreased By ▼ -2.94 (-5.21%)
SNGP 67.25 Increased By ▲ 0.25 (0.37%)
SSGC 10.70 Decreased By ▼ -0.13 (-1.2%)
TELE 8.42 Decreased By ▼ -0.87 (-9.36%)
TPLP 10.75 Decreased By ▼ -0.43 (-3.85%)
TRG 63.87 Decreased By ▼ -5.13 (-7.43%)
UNITY 25.12 Decreased By ▼ -0.37 (-1.45%)
WTL 1.27 Decreased By ▼ -0.05 (-3.79%)
BR100 7,465 Decreased By -57.3 (-0.76%)
BR30 24,199 Decreased By -203.3 (-0.83%)
KSE100 71,103 Decreased By -592.5 (-0.83%)
KSE30 23,395 Decreased By -147.4 (-0.63%)
Print Print 2024-03-06

‘Costly’ coal purchase lands Power Div in a fix

  • 'Catch-22' situation on basis of letter written by former caretaker Federal Minister for Power and Petroleum, Muhammad Ali, who ordered a thorough probe into purchase of coal on higher prices
Published March 6, 2024

ISLAMABAD: The Power Division is reportedly facing a “Catch-22” situation on a letter of former caretaker Federal Minister for Power and Petroleum, Muhammad Ali, who ordered a thorough probe into the purchase of coal by CPEC 1,320-MW Sahiwal Coal Power Plant on higher prices, which are being paid by the consumers, well-informed sources told Business Recorder.

Muhammad Ali wrote the letter, just three days before his departure from the office of caretaker minister, purportedly on complaints he received from the stakeholders.

“Some stakeholders approached the ex-caretaker power minister and apprised him that the contract of coal being purchased by Sahiwal power plant is a long-term one which should be on a bidding basis, and presently it is not transparent as RFP was tailored for one party.

Gwadar coal-fired power plant: PPIB extends financial closing date

The ex-minister secretly probed the matters and found that there was some truthfulness that is why he ordered an inquiry to get to the bottom of the matter.

In March 2022, the National Electric Power Regulatory Authority (Nepra) also warned Chinese imported coal-fired power plants of implications if “legitimate” discount in coal prices is not passed onto the consumers.

The matter was referred by the highest office as serious complaints were received against Chinese imported coal-fired projects that they are siphoning money in the name of coal suppliers.

“These are very serious allegations. Please try to understand. I don’t want to caution you here but take my words very, very, very seriously. Show some very serious effort here; otherwise, I’m warning you for the last time that you will be in deep, deep, deep trouble,” warned the then Chairman Nepra Tauseef H Farooqi.

According to sources, the former caretaker minister, in his letter of March 1, 2024, wrote, reference is made to the complaints received from various stakeholders expressing serious concerns over the fairness and transparency in the bidding process of long-term coal contract in case of Sahiwal coal power.

There is an urgent need to investigate the matter and a comprehensive inquiry must be conducted covering the following aspects with report to be submitted within two weeks; (i) an audit or analysis should be conducted of coal purchases in the past and were these purchases in line with the prevailing rates. If not, what was the loss incurred which affected the consumers or the government; (ii) Why have guidelines for the procurement of coal on PKR purchase on a long-term basis not been issued by Nepra despite the fact that imported coal power plants have been in operation since a long time; (iii) how does Nepra or Power Purchaser, mandated under the relevant PPAs, ensure healthy competition while short-listing coal suppliers in the instant case; (iv) In the absence of specific guidelines from Nepra, were reasonable efforts taken to ensure that the process was transparent, fair and met the expectations of all stakeholders? Specifically, was adequate time provided to submit the bidding documents; (v) Were the terms solicited by Sahiwal Power reasonable and not specific to a supplier; (vi) despite all vendors offering payments in PKR, what criteria were used to select the impugned coal supplier in this case; (vii) given that the fuel price of coal is a pass-through item, has Nepra taken necessary steps to ensure that any potential savings arising from the agreements between the coal supplier and power producers were clawed back for the benefit of the electricity consumers, and (viii) until the inquiry is over, should all purchase contracts which are governed through an updated framework/ guideline, be halted till a standard and comprehensive mechanism is agreed upon with the stakeholders.

Copyright Business Recorder, 2024

Comments

Comments are closed.

T Mar 06, 2024 06:14am
every institution simply dragging their feet, no interest in working.
thumb_up Recommended (0)
E Mar 06, 2024 09:39am
There would be many other such arrangements but fhis one came to light.
thumb_up Recommended (0)
Aan Mar 06, 2024 09:42am
This doubts all CEPEC Power Projects. Imagine solar tariff for CEPEC is @ PKR 50 per units as compare to other solar projects of the same period but having power tariff between 20 to 35 PKR.