AVN 64.80 Increased By ▲ 0.63 (0.98%)
BAFL 30.90 Increased By ▲ 1.00 (3.34%)
BOP 4.73 Increased By ▲ 0.10 (2.16%)
CNERGY 3.87 Decreased By ▼ -0.02 (-0.51%)
DFML 13.44 Increased By ▲ 0.09 (0.67%)
DGKC 41.34 Increased By ▲ 0.49 (1.2%)
EPCL 46.23 Decreased By ▼ -0.77 (-1.64%)
FCCL 11.39 Increased By ▲ 0.39 (3.55%)
FFL 5.05 Decreased By ▼ -0.03 (-0.59%)
FLYNG 5.81 Increased By ▲ 0.04 (0.69%)
GGL 9.90 Increased By ▲ 0.15 (1.54%)
HUBC 64.06 Increased By ▲ 2.11 (3.41%)
HUMNL 5.67 Increased By ▲ 0.02 (0.35%)
KAPCO 27.83 Increased By ▲ 0.25 (0.91%)
KEL 2.13 Decreased By ▼ -0.02 (-0.93%)
LOTCHEM 24.35 Increased By ▲ 0.05 (0.21%)
MLCF 21.36 Increased By ▲ 0.64 (3.09%)
NETSOL 84.43 Increased By ▲ 1.33 (1.6%)
OGDC 87.80 Increased By ▲ 1.75 (2.03%)
PAEL 10.92 Increased By ▲ 0.12 (1.11%)
PIBTL 4.17 Increased By ▲ 0.03 (0.72%)
PPL 77.53 Increased By ▲ 1.34 (1.76%)
PRL 13.65 Decreased By ▼ -0.01 (-0.07%)
SILK 0.88 Decreased By ▼ -0.01 (-1.12%)
SNGP 41.75 Increased By ▲ 1.00 (2.45%)
TELE 5.89 Increased By ▲ 0.01 (0.17%)
TPLP 15.81 Increased By ▲ 0.16 (1.02%)
TRG 112.65 Increased By ▲ 2.55 (2.32%)
UNITY 13.97 Increased By ▲ 0.22 (1.6%)
WTL 1.14 Decreased By ▼ -0.01 (-0.87%)
BR100 4,048 Increased By 80.6 (2.03%)
BR30 14,467 Increased By 282.1 (1.99%)
KSE100 40,673 Increased By 801.8 (2.01%)
KSE30 15,190 Increased By 292.7 (1.96%)
Follow us

ISLAMABAD: World Bank (WB) is likely to allow 22 months extension on the closing date of the $425 million National Transmission Modernization I project (NTMP-1) to regulate delays on different accounts.

The World Bank’s Country Director, Najy Benhassine in a letter to Secretary Economic Affairs, Dr Kazim Niaz has shared the Aide Memoire of the World Bank team that conducted a Mid Term Review (MTR) and implementation support mission for the NTMP-1 held during the period of June 27-July 7, 2022.

The objectives of the mission were to: (i) review the project status of the NTMP-l project, including procurement, contract management, final management, disbursement, and reporting under the project, and ; (ii) discuss the anticipated restructuring of the project and possible fund re-allocation and provide the necessary support to National Transmission and Despatch Company (NTDC) on the implementation of the project.

The project’s component A is the expansion and upgrade of the transmission network- (cost $344.56 million). Component B is comprised of deployment of the Enterprise Resource Planning System: (cost $29.16 million); and component C is project management, technical assistance and capacity building (cost $20 million).

According to the World Bank country director, the following are the key issues and main agreements reached as outcomes of the mission which the Bank is of the view needs to be addressed by the NTDC.

T5HP: WB agrees to amend IBRD, AIIB loan agreements

Project Restructuring. First, based on the MTR findings, several key components of NTMP- I are scheduled to run over the current project closing date of January 31, 2024. Hence, the project needs to be restructured to account for initial delays in commencement due to huge delays in engaging the design consultant for the project. The mission agreed with NTDC for a possible extension of the closing date by an additional 22 months from January 31, 2024, to November 30, 2025 for the project.

Secondly, NTDC has sought to reallocate unused funds from both components B and C to component A with a view to have funds to settle potential extension of time claims. NTDC estimates that it may seek to reallocate $5 million from component C and $3.6 million from component B, totalling $8.6 million to component A. World Bank has requested the Ministry of Economic Affairs (MoEA) and NTDC to work together to submit a Project Restructuring request to World Bank in the coming months.

Islamabad West Substation(IWS): This component is affected by significant delays in the acquisition of land and is on a critical path, due to its role in connecting both Dasu and Tarbela- V hydropower stations. Section 5 has been approved and notified by the Commissioner and this is being followed by the award under Section-l1. World Bank has requested NTDC to fast-track this process of evaluation of trees.

Crops and structures, and start making payments according to the resettlement plan. The technical proposals were received by NTDC for the IWS in December 2021, and the draft Technical Evaluation Report (TER) was shared with the Bank on August 28, after a gap of more than eight months. The TER has been reviewed by the Bank and returned for comments.

Approval of change orders: The Bank is of the view that some contractors were at standstill in the execution of their sub-projects because NTDC had not approved their request for change orders, and in some cases, taking as long as seven months to obtain approvals.

Copyright Business Recorder, 2022

Comments

Comments are closed.

World Bank may allow 22-month extension of NTMP-1 closing date

Dar meets IMF review mission, apprises it of planned power sector reforms

After 29 successive losses, rupee sees some gain, settles at 267.89 against US dollar

US Fed starts policy meeting with smaller rate hike likely

We must put our house in order, says Asif after Peshawar mosque bombing

Corps commanders resolve to bring perpetrators of Peshawar attack to ‘exemplary justice’

Inflationary pressure expected to calm down gradually: Finance Division

KSE-100 jumps 800 points owing to optimism over IMF talks

Pakistan’s performance worsens, rank remains same in corruption perception index

Police foil terrorist attack on Mianwali police station

Barrick Gold makes first payment of $3mn to Balochistan govt