AIRLINK 79.41 Increased By ▲ 1.02 (1.3%)
BOP 5.33 Decreased By ▼ -0.01 (-0.19%)
CNERGY 4.38 Increased By ▲ 0.05 (1.15%)
DFML 33.19 Increased By ▲ 2.32 (7.52%)
DGKC 76.87 Decreased By ▼ -1.64 (-2.09%)
FCCL 20.53 Decreased By ▼ -0.05 (-0.24%)
FFBL 31.40 Decreased By ▼ -0.90 (-2.79%)
FFL 9.85 Decreased By ▼ -0.37 (-3.62%)
GGL 10.25 Decreased By ▼ -0.04 (-0.39%)
HBL 117.93 Decreased By ▼ -0.57 (-0.48%)
HUBC 134.10 Decreased By ▼ -1.00 (-0.74%)
HUMNL 7.00 Increased By ▲ 0.13 (1.89%)
KEL 4.67 Increased By ▲ 0.50 (11.99%)
KOSM 4.74 Increased By ▲ 0.01 (0.21%)
MLCF 37.44 Decreased By ▼ -1.23 (-3.18%)
OGDC 136.70 Increased By ▲ 1.85 (1.37%)
PAEL 23.15 Decreased By ▼ -0.25 (-1.07%)
PIAA 26.55 Decreased By ▼ -0.09 (-0.34%)
PIBTL 7.00 Decreased By ▼ -0.02 (-0.28%)
PPL 113.75 Increased By ▲ 0.30 (0.26%)
PRL 27.52 Decreased By ▼ -0.21 (-0.76%)
PTC 14.75 Increased By ▲ 0.15 (1.03%)
SEARL 57.20 Increased By ▲ 0.70 (1.24%)
SNGP 67.50 Increased By ▲ 1.20 (1.81%)
SSGC 11.09 Increased By ▲ 0.15 (1.37%)
TELE 9.23 Increased By ▲ 0.08 (0.87%)
TPLP 11.56 Decreased By ▼ -0.11 (-0.94%)
TRG 72.10 Increased By ▲ 0.67 (0.94%)
UNITY 24.82 Increased By ▲ 0.31 (1.26%)
WTL 1.40 Increased By ▲ 0.07 (5.26%)
BR100 7,526 Increased By 32.9 (0.44%)
BR30 24,650 Increased By 91.4 (0.37%)
KSE100 71,971 Decreased By -80.5 (-0.11%)
KSE30 23,749 Decreased By -58.8 (-0.25%)
Pakistan

K-Electric to add 450 MW by May 21

  • Conclusion of the interconnection agreement (ICA) with NTDC and PPA with CPPA-G for 2,050 was crucial for off-take of additional power.
Published March 3, 2021

KARACHI: The first 450 MW unit of RLNG-based BQPS-III project is scheduled to come online by May 2021 which would help improve K-Electric’s generation fleet efficiency from 38% in FY 2020 to 48% in FY 2023.

Chief Financial Officer KE, Aamir Ghaziani, in a corporate briefing held via webinar on Wednesday, reiterated KE’s commitment with taking Karachi to a power surplus position by 2022 and informed that upcoming 900 MW RLNG-based BQPS-III is proceeding as per expected timelines while of renewable energy projects of 350 MW were also in the pipeline.

He informed financial analysts from various brokerage houses and financial institutes that Work on the 220 kV Dhabeji Grid and transmission lines has started and finalization of contractual arrangements for the off-take of additional 1,400 MW from National Grid was in advanced stages he said and hoped that the National Transmission & Dispatch Company (NTDC) will complete necessary rehabilitation of the 220 KV Dhabeji grid along with implementation of “Cross Trip” scheme by March of 2021.

Conclusion of the interconnection agreement (ICA) with NTDC and power purchase agreement (PPA) with CPPA-G for 2,050 was crucial for off-take of additional power.

He claimed that KE owing to improved operational and financial indicators has turned around to earning profit in first half of fiscal year 2021 as in the first half of FY 2021 KE have recorded 4.8 % growth in sent-out, improvement in transmission and dispatch (T&D) losses by 0.6 pp and reduction in interest rates.

As part of project Sarbulandi the KE continued with the conversion to Aerial Bundled Cable (ABC) with more than 800 Pole Mounted Transformers (PMT) converted to ABC during first half of FY 2021, and around 10,000 PMTs overall Ghaziani said and claimed that it resulted in reduction of load shedding in Korangi, Orangi and Landhi with up to four hours on average.

Analysts were also briefed about key challenges to the sustainability of the company and project timelines which includes circular debt. As of December 2020, KE’s net receivables from various Federal and Provincial entities stood at around Rs. 77 billion on principal basis, which continue to put a strain on the Company’s cash-flow position.

Significant delays in approval of tariff adjustments, write off claims and investments approval remain a key concern for KE as they lead to significant accumulation of working capital requirement as well as create regulatory uncertainty he said adding that KE remains engaged with NEPRA for earliest resolution of the same.