AIRLINK 80.55 Increased By ▲ 1.14 (1.44%)
BOP 5.28 Decreased By ▼ -0.05 (-0.94%)
CNERGY 4.39 Increased By ▲ 0.01 (0.23%)
DFML 34.79 Increased By ▲ 1.60 (4.82%)
DGKC 76.90 Increased By ▲ 0.03 (0.04%)
FCCL 20.65 Increased By ▲ 0.12 (0.58%)
FFBL 33.50 Increased By ▲ 2.10 (6.69%)
FFL 9.75 Decreased By ▼ -0.10 (-1.02%)
GGL 10.20 Decreased By ▼ -0.05 (-0.49%)
HBL 118.45 Increased By ▲ 0.52 (0.44%)
HUBC 135.60 Increased By ▲ 1.50 (1.12%)
HUMNL 7.04 Increased By ▲ 0.04 (0.57%)
KEL 4.67 No Change ▼ 0.00 (0%)
KOSM 4.70 Decreased By ▼ -0.04 (-0.84%)
MLCF 37.60 Increased By ▲ 0.16 (0.43%)
OGDC 137.00 Increased By ▲ 0.30 (0.22%)
PAEL 23.04 Decreased By ▼ -0.11 (-0.48%)
PIAA 27.17 Increased By ▲ 0.62 (2.34%)
PIBTL 6.91 Decreased By ▼ -0.09 (-1.29%)
PPL 113.40 Decreased By ▼ -0.35 (-0.31%)
PRL 27.49 Decreased By ▼ -0.03 (-0.11%)
PTC 14.75 No Change ▼ 0.00 (0%)
SEARL 57.00 Decreased By ▼ -0.20 (-0.35%)
SNGP 66.67 Decreased By ▼ -0.83 (-1.23%)
SSGC 11.05 Decreased By ▼ -0.04 (-0.36%)
TELE 9.27 Increased By ▲ 0.04 (0.43%)
TPLP 11.58 Increased By ▲ 0.02 (0.17%)
TRG 71.92 Decreased By ▼ -0.18 (-0.25%)
UNITY 25.60 Increased By ▲ 0.78 (3.14%)
WTL 1.36 Decreased By ▼ -0.04 (-2.86%)
BR100 7,590 Increased By 64.4 (0.86%)
BR30 24,769 Increased By 119.8 (0.49%)
KSE100 72,446 Increased By 474.4 (0.66%)
KSE30 23,926 Increased By 177.4 (0.75%)
Business & Finance KEL (K-Electric Limited) 4.67 No Change ▼ 0%

OGRA grants KE license for RLNG pipeline Construction & Operation

  • K-Electric had submitted an application for the same on 18 May 2020, so as to ensure the pipeline would be built in time for the commissioning of the first unit of BQPS-III.
Published January 8, 2021

The Oil and Gas Regulatory Authority (OGRA) has approved K-Electric’s application for a license to construct and operate a gas pipeline, that will supply Re-gasified Liquefied Natural Gas (RLNG) for the upcoming RLNG-based 900 MW BQPS-III power plant and supplementing fuel requirement of the power plants located at its Bin Qasim Power Complex.

In the notification, OGRA grants a License to K-Electric Limited to undertake regulated activity related to construction and operation of 14 inch diameter x 2.4 kilometer Natural Gas Pipeline along with ancillary/connected facilities for purpose of transmission of Natural Gas/RLNG from Tie-in Point, SSGC Custody Transfer Station located at Bin Qasim to KE Bin Qasim Power Complex”

K-Electric had submitted an application for the same on 18 May 2020, so as to ensure the pipeline would be built in time for the commissioning of the first unit of BQPS-III.

It is pertinent to inform that KE has agreed to undertake the construction of the pipeline from the nearest SSGC Custody Transfer Station, on a self-finance basis. The EPC contractor and the Owner Engineer for this pipeline project are already on-board, the detail design of is already completed and the pipeline material has already been procured. Now, with the issuance of License by OGRA, K-Electric has immediately started construction of pipeline for its timely availability for commissioning of 900 MW power plant.

The addition of the 900 MW RLNG Power Plant along with proposed decommissioning of older and less efficient units will ultimately increase the power utility’s generation capacity and lead to improved service delivery.

KE informed that gas turbines and steam generators have arrived and are waiting to be installed so that the first unit of 450 MW can be brought online by summer of 2021, and the second unit by end of 2021.

Meanwhile, Heads of Agreement with Pakistan LNG Limited (PLL) for supply of 150 mmcfd of gas for BQPS-III has already been signed, subsequent to which negotiations on the Gas Sale Agreement (GSA) have reached to the advance stage and any potential hurdles need to be resolved as per past commitments by the Cabinet Committee on Energy (CCoE).

KE said that the 900 MW RLNG based plant and its timely completion is just one step towards keeping Karachi energized. “Even with the commissioning of this plant, NTDC needs to expedite work on the upgrade of the interconnection facilities at the KDA Grid so that the power utility can evacuate the promised additional 450 MW from the National Grid before Summer 2021,” said KE.

Comments

Comments are closed.