AIRLINK 74.63 Decreased By ▼ -0.53 (-0.71%)
BOP 5.42 Decreased By ▼ -0.03 (-0.55%)
CNERGY 4.33 Decreased By ▼ -0.06 (-1.37%)
DFML 28.50 Increased By ▲ 0.86 (3.11%)
DGKC 77.14 Increased By ▲ 5.14 (7.14%)
FCCL 21.44 Increased By ▲ 1.15 (5.67%)
FFBL 31.32 Increased By ▲ 0.27 (0.87%)
FFL 10.21 Increased By ▲ 0.24 (2.41%)
GGL 10.69 Increased By ▲ 0.42 (4.09%)
HBL 114.80 Decreased By ▼ -0.20 (-0.17%)
HUBC 130.60 Decreased By ▼ -0.85 (-0.65%)
HUMNL 6.83 Decreased By ▼ -0.04 (-0.58%)
KEL 4.10 Decreased By ▼ -0.10 (-2.38%)
KOSM 4.78 Increased By ▲ 0.01 (0.21%)
MLCF 39.78 Increased By ▲ 2.70 (7.28%)
OGDC 134.90 Decreased By ▼ -0.55 (-0.41%)
PAEL 23.75 Increased By ▲ 0.35 (1.5%)
PIAA 27.41 Increased By ▲ 0.10 (0.37%)
PIBTL 6.65 Increased By ▲ 0.05 (0.76%)
PPL 113.60 Increased By ▲ 0.44 (0.39%)
PRL 28.61 Decreased By ▼ -0.14 (-0.49%)
PTC 15.33 Decreased By ▼ -0.17 (-1.1%)
SEARL 57.74 Increased By ▲ 0.41 (0.72%)
SNGP 67.26 Increased By ▲ 0.27 (0.4%)
SSGC 11.19 Increased By ▲ 0.02 (0.18%)
TELE 9.23 Increased By ▲ 0.09 (0.98%)
TPLP 12.06 Increased By ▲ 0.01 (0.08%)
TRG 70.50 Increased By ▲ 0.11 (0.16%)
UNITY 23.76 Increased By ▲ 0.11 (0.47%)
WTL 1.35 Increased By ▲ 0.01 (0.75%)
BR100 7,475 Increased By 20 (0.27%)
BR30 24,369 Increased By 119.1 (0.49%)
KSE100 71,711 Increased By 277.3 (0.39%)
KSE30 23,640 Increased By 73.9 (0.31%)

imageISLAMABAD: As many as 35 wind power projects having a cumulative capacity of 1749.2 MW are at different stages of development which will be operationalized by 2018.

Official sources in Alternative Energy Development Board (AEDB) told APP that some 12 wind projects of 587.2 MW had already been supplying electricity to the national grid system.

They said these projects included 50 MW FFC Energy Limited, 56.4 MW Zorlu Emerji Pakistan, 49.5 MW Three Gorges First Wind Farm Pakistan (Pvt.) Ltd, 50 MW Foundation WInd Energy-II Ltd, 50 MW Foundation Wind Energy II Ltd, 52.8 MW Sapphire Wind Power Company Ltd, 50 MW Yunus Energy Ltd, 50 MW Metro Power Company Ltd, 49.5 MW Tapal Wind Energy Pvt. Ltd, 30 MW Tenga Generasi Ltd, 50 MW Master Wind Energy Ltd and 49.5 MW Gul Wind Energy Ltd.

The sources said five projects having 298 MW capacity had also achieved financial close and were under construction.

Giving the details of the projects, they said 49.5 MW Hydro China Dawood Power Pvt Ltd (Thatta) would be ready by November 2016, 49.5 MW Sachal Energy Development Pvt Ltd in May 2017, 99 MW United Energy Ltd in September and 50 MW each Jhampir Wind Power Ltd and Hawa Energy Ltd by February 2018.

They said some 18 wind projects of 864 MW were at different stages of development and expected to be completed by 2018.

These projects included 50 MW each Three Gorge Second Wind Farm Pvt. Ltd, FFC Energy Limited, Tricon Boston Consulting Corporation Pvt. Limited, Tricon Boston Consulting Corporation Pvt. Limited,Tricon Boston Consulting Corporation Pvt. Limited, Western Energy Pvt. Limited, Hartford Alternative Energy Pvt. Limited, Zephyr Power (Pvt.) Ltd, Shaheen Foundation, Trans Atlantic Energy Pvt. Ltd.,Norinco International Thatta Power Pvt. Ltd., Act 2 Wind Ltd., Artistic Wind Power Pvt. Ltd., Harvey Wind Power Project , Zulikha Energy Ltd, Gul Ahmed Electric Ltd., Din Energy Ltd. and 14 MW Burj

Wind Energy Pvt. Limited.

They said all these projects were being set up in district Thatta.

Copyright APP (Associated Press of Pakistan), 2016

Comments

Comments are closed.