AIRLINK 74.85 Increased By ▲ 0.56 (0.75%)
BOP 4.98 Increased By ▲ 0.03 (0.61%)
CNERGY 4.49 Increased By ▲ 0.12 (2.75%)
DFML 40.00 Increased By ▲ 1.20 (3.09%)
DGKC 86.35 Increased By ▲ 1.53 (1.8%)
FCCL 21.36 Increased By ▲ 0.15 (0.71%)
FFBL 33.85 Decreased By ▼ -0.27 (-0.79%)
FFL 9.72 Increased By ▲ 0.02 (0.21%)
GGL 10.45 Increased By ▲ 0.03 (0.29%)
HBL 112.74 Decreased By ▼ -0.26 (-0.23%)
HUBC 137.44 Increased By ▲ 1.24 (0.91%)
HUMNL 11.42 Decreased By ▼ -0.48 (-4.03%)
KEL 5.28 Increased By ▲ 0.57 (12.1%)
KOSM 4.63 Increased By ▲ 0.19 (4.28%)
MLCF 37.80 Increased By ▲ 0.15 (0.4%)
OGDC 139.50 Increased By ▲ 3.30 (2.42%)
PAEL 25.61 Increased By ▲ 0.51 (2.03%)
PIAA 20.68 Increased By ▲ 1.44 (7.48%)
PIBTL 6.80 Increased By ▲ 0.09 (1.34%)
PPL 122.20 Increased By ▲ 0.10 (0.08%)
PRL 26.58 Decreased By ▼ -0.07 (-0.26%)
PTC 14.05 Increased By ▲ 0.12 (0.86%)
SEARL 58.98 Increased By ▲ 1.76 (3.08%)
SNGP 68.95 Increased By ▲ 1.35 (2%)
SSGC 10.30 Increased By ▲ 0.05 (0.49%)
TELE 8.38 Decreased By ▼ -0.02 (-0.24%)
TPLP 11.06 Decreased By ▼ -0.07 (-0.63%)
TRG 64.19 Increased By ▲ 1.38 (2.2%)
UNITY 26.55 Increased By ▲ 0.05 (0.19%)
WTL 1.45 Increased By ▲ 0.10 (7.41%)
BR100 7,841 Increased By 30.9 (0.4%)
BR30 25,465 Increased By 315.4 (1.25%)
KSE100 75,114 Increased By 157.8 (0.21%)
KSE30 24,114 Increased By 30.8 (0.13%)

ISLAMABAD: The “Sindh Barrages Improvement Project” of worth $326.6 million is facing financing gap of about $72 million and will require either government of Sindh counterpart funding or additional IDA funding to meet contractual obligations in the medium-term. Official documents of the World Bank revealed that due to accumulated delays, completing the works at Guddu and Sukkur will require more time beyond the current project closing date of June 30, 2024.

The project was approved in 2015 with development objectives to improve the reliability and safety of the Guddu barrage and strengthen the Sindh Irrigation Department’s capacity to operate and manage the barrage. The original closing date was 22 December 2020, which was later revised to June 30, 2024.

The bank has rated the progress towards achievement of project development objective and overall implementation progress as moderately satisfactory.

World Bank terms implementation progress of Sindh Resilience Project ‘satisfactory’

The project has made substantial progress. Works at Guddu are progressing and have reached 48 per cent physical progress for the barrage and substantial completion for the river training works. Remaining river training works at Right TJ Spur are yet to be launched.

The rehabilitation of Sukkur barrage started in February 2023 and shows a steady progress and currently at 4.5 per cent physical progress. Moreover, the project has a financing gap of about $72 million and will require either the GoS counterpart funding or additional IDA funding to meet contractual obligations in the medium-term.

The Government of Sindh has processed a Planning Commission form 1 (PC-1) amalgamating the previous two separate PC-1, one for Guddu and one for Sukkur, and reflecting the new financing requirement and extended timeframe.

On the institutional side, the Government of Sindh has established a Barrage Management Unit (BMU) headed by a chief engineer to oversee the operation and maintenance of the three barrages in Sindh (Guddu, Sukkur, and Kotri). The capacity of BMU will be strengthened under the project’s component B supporting Improved Barrage Operation, the bank noted.

Documents noted that six gate leaves have been replaced but their hoisting systems have not been replaced yet. Both gate and hoisting system to be replaced to count for additional flood passage capacity.

Copyright Business Recorder, 2023

Comments

Comments are closed.