BR100 Decreased By (-0.4%)
BR30 Decreased By (-0.65%)
KSE100 Decreased By (-0.29%)
KSE30 Decreased By (-0.22%)
AGHA 6.56 Decreased By ▼ -0.11 (-1.65%)
BECO 4.40 Increased By ▲ 0.05 (1.15%)
BML 55.89 Decreased By ▼ -0.28 (-0.5%)
BOP 30.05 Decreased By ▼ -0.07 (-0.23%)
CNERGY 12.75 Decreased By ▼ -0.23 (-1.77%)
CSIL 5.21 Decreased By ▼ -0.10 (-1.88%)
FCCL 51.00 Decreased By ▼ -0.65 (-1.26%)
FFL 14.43 Decreased By ▼ -0.06 (-0.41%)
FNEL 1.22 Increased By ▲ 0.01 (0.83%)
KEL 5.97 Decreased By ▼ -0.09 (-1.49%)
KOSM 5.58 Decreased By ▼ -0.26 (-4.45%)
LOTCHEM 26.15 Decreased By ▼ -0.02 (-0.08%)
MLCF 90.33 Decreased By ▼ -0.90 (-0.99%)
NBP 161.45 Decreased By ▼ -2.74 (-1.67%)
NCPL 52.55 Decreased By ▼ -0.63 (-1.18%)
NPL 57.98 Decreased By ▼ -1.14 (-1.93%)
OGDC 315.40 Increased By ▲ 2.01 (0.64%)
PACE 9.70 Decreased By ▼ -0.07 (-0.72%)
PAEL 34.73 Decreased By ▼ -0.51 (-1.45%)
PIBTL 14.23 Decreased By ▼ -0.48 (-3.26%)
PPL 221.00 Decreased By ▼ -0.36 (-0.16%)
PRL 90.89 Decreased By ▼ -0.33 (-0.36%)
PTC 59.25 Increased By ▲ 0.06 (0.1%)
SSGC 23.39 Increased By ▲ 0.09 (0.39%)
TBL 8.65 Decreased By ▼ -0.10 (-1.14%)
TELE 7.40 Decreased By ▼ -0.21 (-2.76%)
TPL 21.00 Decreased By ▼ -1.03 (-4.68%)
TPLP 12.02 Decreased By ▼ -0.54 (-4.3%)
TREET 21.33 Decreased By ▼ -0.40 (-1.84%)
TRG 54.35 Decreased By ▼ -1.44 (-2.58%)
Markets

Qatargas plans several LNG outages in autumn

DUBAI : Qatargas will stop three of the world's biggest liquefied natural gas (LNG) producing plants at different times
Published Updated

qatarasDUBAI: Qatargas will stop three of the world's biggest liquefied natural gas (LNG) producing plants at different times during a rolling maintenance programme planned for this autumn, the world's largest LNG producer said on Sunday.

European gas prices leapt on Friday after traders with knowledge of the situation told Reuters Qatargas trains 5, 6 and 7 would shut consecutively for around two weeks each from mid September to early November when heating demand from big buyers in Europe and north-east Asia climbs as temperatures fall.

Qatargas did not give exact dates or durations on Sunday for the closures of its three newest production lines each able to produce 7.8 million tonnes a year (mtpa) of LNG but said it also planned to do work on parts of the 7.8 mtpa train 4 and 3.2 mtpa train 3.

"Qatargas can confirm that the planned maintenance of its Trains 5, 6 and 7, as well as Qatargas 3 and 4 inlet receiving facilities will take place this autumn," a spokesperson from Qatargas in a statement on Sunday.

"Qatargas operates a rolling programme of planned maintenance at its facilities.

These necessary, planned and safe shutdowns are coordinated with all parties of our operations, shipping and customers as part of our annual planning exercises. There will be no impact on our existing customer portfolio."

On Friday, traders familiar with the plans said work at trains 5-7 was expected to last for about two weeks each, also reducing Qatari condensate production while the huge processing plants attached to Qatar's vast North Field are down.

Qatargas did not comment on whether the inlet receiving facility work would require the complete shutdown of trains 3 or 4. Some inlet receiving systems can be bypassed so that production can be maintained, while others require a complete shutdown, an industry source said.

British benchmark front-season gas prices soared six percent on Friday on fears the maintenance could cut supply to north west European consumers already worried about Qatari LNG diversions to higher paying Japan, where gas demand has boomed since a March earthquake shut nuclear power plants.

Qatargas operates seven LNG trains with a capacity of 42 million tonnes per annum (mtpa), but has signed several deals since March to sell more LNG to new markets in addition to Japan.

Copyright Reuters, 2011