BR100 Decreased By (-0.25%)
BR30 Decreased By (-0.64%)
KSE100 Decreased By (-0.41%)
KSE30 Decreased By (-0.67%)
BECO 5.83 Decreased By ▼ -0.20 (-3.32%)
BML 57.90 Increased By ▲ 5.15 (9.76%)
BOP 33.79 Decreased By ▼ -0.46 (-1.34%)
CNERGY 8.15 Decreased By ▼ -0.01 (-0.12%)
DCL 11.79 Decreased By ▼ -0.55 (-4.46%)
FCCL 53.49 Decreased By ▼ -0.40 (-0.74%)
FCSC 5.40 Increased By ▲ 0.18 (3.45%)
FFL 17.84 Decreased By ▼ -0.19 (-1.05%)
FNEL 1.30 No Change ▼ 0.00 (0%)
HUMNL 11.11 Increased By ▲ 0.11 (1%)
KEL 8.02 Decreased By ▼ -0.09 (-1.11%)
KOSM 5.45 Increased By ▲ 0.07 (1.3%)
MLCF 87.40 Decreased By ▼ -0.65 (-0.74%)
NBP 184.24 Decreased By ▼ -2.24 (-1.2%)
PACE 11.62 Increased By ▲ 0.90 (8.4%)
PAEL 40.25 Increased By ▲ 0.31 (0.78%)
PIAHCLA 26.12 Decreased By ▼ -0.05 (-0.19%)
PIBTL 17.14 Decreased By ▼ -0.18 (-1.04%)
PPL 228.73 Decreased By ▼ -4.05 (-1.74%)
PRL 34.49 Decreased By ▼ -0.46 (-1.32%)
PTC 67.54 Decreased By ▼ -0.02 (-0.03%)
SEARL 90.93 No Change ▼ 0.00 (0%)
SSGC 26.83 Decreased By ▼ -0.34 (-1.25%)
TELE 8.53 Decreased By ▼ -0.04 (-0.47%)
THCCL 66.14 Increased By ▲ 6.01 (10%)
TPLP 9.33 Increased By ▲ 0.57 (6.51%)
TREET 24.51 Decreased By ▼ -0.03 (-0.12%)
TRG 71.61 Decreased By ▼ -0.14 (-0.2%)
WAVES 10.98 Increased By ▲ 1.00 (10.02%)
WTL 1.28 Increased By ▲ 0.02 (1.59%)
Pakistan

87.23 pc civil work on LOMTP completed

LAHORE: Public will soon hear good news about the trial run of Lahore Orange Line Metro Train as excavation work fro
Published April 18, 2018 Updated April 18, 2018 07:41pm

LAHORE: Public will soon hear good news about the trial run of Lahore Orange Line Metro Train as excavation work from the remaining portion of 1.7 km long cut and cover portion has been completed connecting both ends of the 27 kilo meters long viaduct of the train from Dera Gujjran to Ali Town.

Advisor to the Chief Minister, Punjab and Chairman of the steering committee for Lahore Orange Line Metro Train Project (LOMTP) Khawaja Ahmad Hassan revealed this after the weekly progress review meeting here Wednesday.

This was a major milestone for the project as last hurdle in this public friendly project has been removed as a result of digging the remaining part of the barrel for the train, he added.

The meeting was told that so far 87.23 per cent civil work on the project had been completed.

Progress of work on package-I from Dera Gujjaran, G.T.Road to Chouburji was 91.27 per cent, on package-II from Choburji to Ali Town was 81.35 per cent, on Depot near Dera Gujran was 87.31 per cent while on Stabling Yard near Ali Town it was 88.81 per cent.

Progress on electrical and mechanical work on the project had been 63.70 per cent.

The work for laying metallic track as well as installation of electrical and mechanical equipment was in full swing these days as additional work force had been employed by the Chinese contractor CR-NORINCO for this purpose with a view to partially starting the trial run of the train very soon, he revealed.

The meeting was informed that the Parks and Horticulture Authority had been tasked for designing ornamental lightening system for illumination of track as per international standards.

The train will be operated with electricity and construction of an electric sub-station near University of Engineering and Technology at G.T. Road had been completed for this purpose. LESCO had assured to make it functional as and when required.

The meeting was further told that first five metro stations from Dera Gujjaran to Pakistan Mint have been completed while Nichelson Road station will be completed by the end of next week. More than half of the track laying work at this stretch had already been completed, he said.

Khawaja Ahmad Hassan directed for completing rehabilitation and reconstruction of roads, affected by the ongoing civil work, by the end of this month for ending the sufferings of the general public as well as the local traders. He urged the departments concerned to finalize shifting of utility services for this purpose before the carpeting of roads as road cuts will not be allowed after the construction of roads is finalized.

MNA Maher Ishtiaq, MPA Bao Akhter Ali, General Manager NESPAK Salman Hafeez, Chief Engineer TEPA, LDA Mazhar Hussain Khan, senior officials of LESCO, WASA, PTCL, SUI GAS, Traffic Police, Railways, Rescue 1122, Civil Defence, Chinese Contractor, CR- NOROINCO, Representatives of Chinese Engineering Consultant and local contractors of the project attended the meeting.

Copyright APP (Associated Press of Pakistan), 2018

Comments

Comments are closed for this article.