BR100 Decreased By (-1.39%)
BR30 Decreased By (-1.72%)
KSE100 Decreased By (-1.3%)
KSE30 Decreased By (-1.25%)
AGHA 7.92 Decreased By ▼ -0.17 (-2.1%)
BECO 5.20 Decreased By ▼ -0.07 (-1.33%)
BML 59.25 Decreased By ▼ -0.13 (-0.22%)
BOP 33.68 Decreased By ▼ -0.51 (-1.49%)
CNERGY 9.81 Increased By ▲ 0.19 (1.98%)
CSIL 5.42 Decreased By ▼ -0.08 (-1.45%)
FCCL 53.52 Decreased By ▼ -0.63 (-1.16%)
FFL 16.68 Decreased By ▼ -0.16 (-0.95%)
FNEL 1.21 Decreased By ▼ -0.02 (-1.63%)
KEL 7.35 Decreased By ▼ -0.24 (-3.16%)
KOSM 5.61 Decreased By ▼ -0.07 (-1.23%)
LOTCHEM 29.11 Decreased By ▼ -1.32 (-4.34%)
MLCF 95.50 Decreased By ▼ -2.66 (-2.71%)
NBP 204.35 Decreased By ▼ -4.44 (-2.13%)
NCPL 58.24 Decreased By ▼ -1.37 (-2.3%)
NPL 67.79 Decreased By ▼ -2.08 (-2.98%)
OGDC 317.94 Decreased By ▼ -5.42 (-1.68%)
PACE 10.71 Decreased By ▼ -0.36 (-3.25%)
PAEL 41.83 Decreased By ▼ -0.42 (-0.99%)
PIBTL 16.50 Decreased By ▼ -0.32 (-1.9%)
PPL 219.74 Decreased By ▼ -4.99 (-2.22%)
PRL 44.59 Increased By ▲ 2.94 (7.06%)
PTC 70.77 Decreased By ▼ -0.35 (-0.49%)
SSGC 28.93 Decreased By ▼ -0.38 (-1.3%)
TBL 9.84 Decreased By ▼ -0.12 (-1.2%)
TELE 8.76 Decreased By ▼ -0.23 (-2.56%)
TPL 16.45 Decreased By ▼ -0.07 (-0.42%)
TPLP 12.10 Decreased By ▼ -0.67 (-5.25%)
TREET 22.80 Decreased By ▼ -0.26 (-1.13%)
TRG 60.03 Decreased By ▼ -0.42 (-0.69%)
Markets

Lucky to install 25.3MW captive solar power project in Karachi at estimated cost of Rs3bn

  • Announces agreement with Orient Energy Systems
Published Updated

Lucky Cement Limited, one of Pakistan’s biggest cement manufacturers, announced entering into an arrangement with Orient Energy Systems (Private) Limited, an engineering company, for the supply and installation of 25.3 MW captive solar power project at its Karachi plant.

In a notice sent to the Pakistan Stock Exchange (PSX) on Wednesday, the cement manufacturer shared that the estimated cost of the project is Rs3 billion

“The company is in the process of establishing Letter of Credit (LCs) for import of equipment, which is subject to receiving approval from the State Bank of Pakistan (SBP),” read the notice.

The project is expected to be completed in approximately eight months after the establishment of LC, said the company.

It added that the power project is in addition to the earlier announced 34MW captive solar power project with a 5.589MW Reflex energy storage at the company's plant in Pezu, Lakki Marwat.

“Sustainability and adoption of clean energy has remained a cornerstone of the Company's strategy and it was one of the first cement companies to install waste heat recovery (WHR) units at both its plant sites.

“The company's initiatives for investment in renewable energy projects will play a key role in cost savings as well as reduction of country's reliance on imported fuel.”

Earlier in June, Lucky Cement’s Board of Directors authorised its management to undertake a feasibility study for a renewable energy project at its plant in Karachi.

Moreover, back in March, Lucky Electric Power Company Limited (LEPCL), a wholly-owned subsidiary of Lucky Cement, successfully completed the commissioning of its 660MW supercritical, lignite coal-based power plant at Deh Ghangiaro, Bin Qasim, Karachi.

The power plant was synchronised with the national grid towards the end of CY 2021 and achieved Commercial Operations Date (COD) on March 21, 2022.

Comments

Comments are closed for this article.

Tariq Sep 15, 2022 04:46pm
Need estimate of 5 Mega watts system with all accessories power factors ect.
0
Gul Farooq Sep 15, 2022 08:56pm
Waoo its good initiative and best wishes for lucky
0
Arif Aslam Khan Sep 16, 2022 05:09am
@Tariq, between USD2.5 Million to USD 3Million max. arifkhan@[email protected]
0