BR100 Increased By (1.77%)
BR30 Increased By (1.96%)
KSE100 Increased By (1.59%)
KSE30 Increased By (1.65%)
BECO 5.62 Increased By ▲ 0.04 (0.72%)
BML 59.51 Decreased By ▼ -1.71 (-2.79%)
BOP 34.61 Increased By ▲ 0.93 (2.76%)
CNERGY 8.08 No Change ▼ 0.00 (0%)
DCL 12.05 Increased By ▲ 0.41 (3.52%)
FCCL 54.40 Increased By ▲ 2.26 (4.33%)
FCSC 5.52 Decreased By ▼ -0.11 (-1.95%)
FFL 18.05 Increased By ▲ 0.04 (0.22%)
FNEL 1.33 Decreased By ▼ -0.02 (-1.48%)
HUMNL 11.07 Increased By ▲ 0.03 (0.27%)
KEL 8.05 Increased By ▲ 0.21 (2.68%)
KOSM 5.88 Increased By ▲ 0.15 (2.62%)
MLCF 90.52 Increased By ▲ 4.01 (4.64%)
NBP 190.17 Increased By ▲ 5.87 (3.19%)
PACE 11.53 Decreased By ▼ -0.12 (-1.03%)
PAEL 41.07 Increased By ▲ 1.11 (2.78%)
PIAHCLA 25.84 Increased By ▲ 0.17 (0.66%)
PIBTL 17.51 Increased By ▲ 0.24 (1.39%)
PPL 225.84 Increased By ▲ 3.17 (1.42%)
PRL 34.63 Increased By ▲ 0.17 (0.49%)
PTC 64.62 Increased By ▲ 0.88 (1.38%)
SEARL 91.38 Increased By ▲ 0.92 (1.02%)
SSGC 26.97 Increased By ▲ 0.30 (1.12%)
TELE 8.93 Increased By ▲ 0.02 (0.22%)
THCCL 69.16 Increased By ▲ 0.69 (1.01%)
TPLP 10.90 Decreased By ▼ -0.30 (-2.68%)
TREET 24.64 Decreased By ▼ -0.06 (-0.24%)
TRG 69.78 Decreased By ▼ -0.81 (-1.15%)
WAVES 11.16 Increased By ▲ 0.05 (0.45%)
WTL 1.27 No Change ▼ 0.00 (0%)

ISLAMABAD: Pakistan Railways has submitted the final draft of six sub-projects of Phase-I for the expansion and up gradation of Main Line (ML-1) under China-Pak Economic Corridor (CPEC).

“On the basis of preliminary design, the PC-I of Phase-I of six sub-projects’ with the cost of 3400 million USD has been submitted to Ministry of Planning Development and Reform,” sources in the Ministry of Railways told APP.

The sources said there is no delay in the start of MI-I project under CPEC, in fact it is a huge, multi­disciplinary project, at an estimated cost of USD 8.2 billion which is likely to increase on finalization of preliminary design for the bidding process.

As a matter of fact due diligence and prudence, in finalization of this huge project, is taking time which is considered essential for processing the project cycle, they added.

“Up-gradation of ML-I of Pakistan Railways (Karachi to Peshawar and Taxila to Havelian) and establishment of dry port near Havelian is an `Early Harvest Project` under CPEC framework,” they said. They said it is spread over 1876 kilometers and starting from Karachi passes through Hyderabad, Rhori, Multan, Lahore, Rawalpindi to Peshawar and Taxila to Havelian.

The sources said the project has been divided into two phases, Phase-I and Phase-II. To fulfill the requirement of Central Development Working Party (CDWP), preliminary design of the project was started in 2016.

“After approval of PC-I, Engineering, Procurement and construction contractor will be appointed through competitive bidding process among Chinese firms, as per inter­governmental framework agreement,” they said.

The sources said in view of this position, it would not be possible to commit any time line for commencement of the work.

Copyright APP (Associated Press of Pakistan), 2018