AIRLINK 80.60 Increased By ▲ 1.19 (1.5%)
BOP 5.26 Decreased By ▼ -0.07 (-1.31%)
CNERGY 4.52 Increased By ▲ 0.14 (3.2%)
DFML 34.50 Increased By ▲ 1.31 (3.95%)
DGKC 78.90 Increased By ▲ 2.03 (2.64%)
FCCL 20.85 Increased By ▲ 0.32 (1.56%)
FFBL 33.78 Increased By ▲ 2.38 (7.58%)
FFL 9.70 Decreased By ▼ -0.15 (-1.52%)
GGL 10.11 Decreased By ▼ -0.14 (-1.37%)
HBL 117.85 Decreased By ▼ -0.08 (-0.07%)
HUBC 137.80 Increased By ▲ 3.70 (2.76%)
HUMNL 7.05 Increased By ▲ 0.05 (0.71%)
KEL 4.59 Decreased By ▼ -0.08 (-1.71%)
KOSM 4.56 Decreased By ▼ -0.18 (-3.8%)
MLCF 37.80 Increased By ▲ 0.36 (0.96%)
OGDC 137.20 Increased By ▲ 0.50 (0.37%)
PAEL 22.80 Decreased By ▼ -0.35 (-1.51%)
PIAA 26.57 Increased By ▲ 0.02 (0.08%)
PIBTL 6.76 Decreased By ▼ -0.24 (-3.43%)
PPL 114.30 Increased By ▲ 0.55 (0.48%)
PRL 27.33 Decreased By ▼ -0.19 (-0.69%)
PTC 14.59 Decreased By ▼ -0.16 (-1.08%)
SEARL 57.00 Decreased By ▼ -0.20 (-0.35%)
SNGP 66.75 Decreased By ▼ -0.75 (-1.11%)
SSGC 11.00 Decreased By ▼ -0.09 (-0.81%)
TELE 9.11 Decreased By ▼ -0.12 (-1.3%)
TPLP 11.46 Decreased By ▼ -0.10 (-0.87%)
TRG 70.23 Decreased By ▼ -1.87 (-2.59%)
UNITY 25.20 Increased By ▲ 0.38 (1.53%)
WTL 1.33 Decreased By ▼ -0.07 (-5%)
BR100 7,629 Increased By 103 (1.37%)
BR30 24,842 Increased By 192.5 (0.78%)
KSE100 72,739 Increased By 767.9 (1.07%)
KSE30 24,033 Increased By 284.2 (1.2%)

ISLAMABAD: The federal government has authorised/disbursed Rs193.15 billion, including Rs38.94 billion foreign aid, while Rs74.91 billion expenditures were made for development projects under the Public-Sector Development Programme (PSDP) 2022-23 from July to September against the total allocation of Rs727 billion.

According to a summary of the PSDP-2022-23 available with Business Recorder, the federal government has authorised/disbursed a total of 139.84 billion including Rs7.565 billion foreign aid, whereas, a total of Rs41.779 billion expenditures were made for various ministries, divisions, and related departments out of Rs566.56 billion allocation.

The government also authorised a total of Rs53.21 billion including Rs31.37 billion foreign aid,whereas,Rs33.064 billion expenditures were made out of Rs159.94 billion for development projects of corporations; a total of Rs29.83 billion including Rs13.878 billion foreign aid has been authorised for development projects of the National Highways Authority (NHA), whereas, Rs13.879 billion expenditures were made. The government has authorised Rs23.377 billion including Rs17.495 billion foreign aid, whereas, Rs19.185 billion expenditures were made out of Rs42.68 billion for the National Transmission and Despatch Company (NTDC)/Pakistan Electric Power Company (Pepco).

The government authorised a total of Rs23.43 billion out of Rs140.64 billion allocation, whereas, Rs11.178 billion were expended for provinces and Special Areas.

Weekly PSDP disbursement: Data uploading abandoned by ministry?

The government authorised 2.393 billion and made 112.73 million expenditures out of 12.65 billion allocations for development projects of the National Health Services, Regulations and Coordination Division.

A total of Rs68 billion while Rs0.40 million were made expenditures for development projects of the Cabinet Division against Rs68.058 allocation.

The government disbursed/authorised 286.46 million out of Rs1.66 billion allocation while Rs7.4 million were expended for development projects of the Finance Division.

The government authorised Rs4.488 billion against Rs32.65 billion allocation but no expenditures were made so far for development projects of the Railway Division. A total of Rs1.865 billion has been authorised out of Rs10.12 billion allocation while Rs637.1 million were made expenditures for development projects of the National Food Security and Research Division.

The government has authorised/disbursed a total of Rs7.779 billion out of Rs44.72 billion while Rs1.32 billion were expended for development projects of the Higher Education Commission and Rs1.25 billion has been authorised for development projects of the Federal Education and Professional Training Division.

The government made expenditures of Rs15.23 billion out of Rs97.56 billion budgeted allocation for the Water Resources Division, Rs3.545 billion has been authorised out of Rs17.73 billion allocation, while Rs1.08 billion expenditures were made for development projects of the Housing and Works Division.

The government has authorised Rs1.9 billion out of Rs9.5 billion allocation, whereas, Rs25.13 million expenditures were made for development projects of the Climate Change Division, Rs1.61 billion has been authorised while Rs249.63 million expenditures were made for development projects of the Interior Division The government has authorised Rs100 million while Rs67.29 million expenditures were made for the development project of the Earthquake Reconstruction and Rehabilitation Authority (Erra).