AIRLINK 72.59 Increased By ▲ 3.39 (4.9%)
BOP 4.99 Increased By ▲ 0.09 (1.84%)
CNERGY 4.29 Increased By ▲ 0.03 (0.7%)
DFML 31.71 Increased By ▲ 0.46 (1.47%)
DGKC 80.90 Increased By ▲ 3.65 (4.72%)
FCCL 21.42 Increased By ▲ 1.42 (7.1%)
FFBL 35.19 Increased By ▲ 0.19 (0.54%)
FFL 9.33 Increased By ▲ 0.21 (2.3%)
GGL 9.82 Increased By ▲ 0.02 (0.2%)
HBL 112.40 Decreased By ▼ -0.36 (-0.32%)
HUBC 136.50 Increased By ▲ 3.46 (2.6%)
HUMNL 7.14 Increased By ▲ 0.19 (2.73%)
KEL 4.35 Increased By ▲ 0.12 (2.84%)
KOSM 4.35 Increased By ▲ 0.10 (2.35%)
MLCF 37.67 Increased By ▲ 1.07 (2.92%)
OGDC 137.75 Increased By ▲ 4.88 (3.67%)
PAEL 23.41 Increased By ▲ 0.77 (3.4%)
PIAA 24.55 Increased By ▲ 0.35 (1.45%)
PIBTL 6.63 Increased By ▲ 0.17 (2.63%)
PPL 125.05 Increased By ▲ 8.75 (7.52%)
PRL 26.99 Increased By ▲ 1.09 (4.21%)
PTC 13.32 Increased By ▲ 0.24 (1.83%)
SEARL 52.70 Increased By ▲ 0.70 (1.35%)
SNGP 70.80 Increased By ▲ 3.20 (4.73%)
SSGC 10.54 No Change ▼ 0.00 (0%)
TELE 8.33 Increased By ▲ 0.05 (0.6%)
TPLP 10.95 Increased By ▲ 0.15 (1.39%)
TRG 60.60 Increased By ▲ 1.31 (2.21%)
UNITY 25.10 Decreased By ▼ -0.03 (-0.12%)
WTL 1.28 Increased By ▲ 0.01 (0.79%)
BR100 7,546 Increased By 137.4 (1.85%)
BR30 24,809 Increased By 772.4 (3.21%)
KSE100 71,902 Increased By 1235.2 (1.75%)
KSE30 23,595 Increased By 371 (1.6%)
Business & Finance

Nord Stream 2 delays resuming pipeline construction: report

  • The consortium will probably be able to say at the end of January or in early February when work will resume, the spokesman said.
  • The construction of a 2.6-km long portion of the pipeline in Germany's shallow waters was resumed and finished last month with the help of the Fortuna.
Published January 15, 2021

BERLIN: The Russia-led Nord Stream 2 consortium is not resuming work to complete the subsea gas pipeline to Germany just yet, daily Handelsblatt reported on Friday, citing a consortium spokesman, amid pressure from Washington to halt the project.

A Danish maritime regulator said last month construction work would resume in Danish waters in mid-January, with a vessel called Fortuna laying the pipes.

"We have permission from the Danish energy agency to start work from Friday. However, this does not mean that we will also resume laying pipes on Friday," Handelsblatt quoted the Nord Stream 2 spokesman as saying.

The consortium will probably be able to say at the end of January or in early February when work will resume, the spokesman said, according to the report.

Nord Stream 2 has not responded to requests for comments. According to Refinitiv Eikon shiptracking data, the Fortuna was anchored near the German port of Rostock on Friday.

Construction of Nord Stream 2 was initially halted in December 2019 following the threat of sanctions from the United States, which wants to cut Europe's dependence on Russian energy and sell its own liquefied natural gas to the region.

The construction of a 2.6-km long portion of the pipeline in Germany's shallow waters was resumed and finished last month with the help of the Fortuna.

Nord Stream 2, designed to double capacity of the existing undersea Nord Stream gas pipeline from Russia to Germany to 110 billion cubic metres (bcm) per year, more than half of Russia's overall pipeline gas exports to Europe.

Separately, Germany's maritime authority said on Friday it had given Nord Stream 2 permission to lay pipelines in its exclusive economic zone from the end of September to the end of May following an application from the consortium in June 2020.

The consortium, led by Russian gas giant Gazprom, still has to lay more than 100 km (62 miles) of the pipeline, which will have annual capacity to pump 55 bcm of gas. More than 90% of the project has been completed.

Gazprom's western partners in the project, which is estimated to cost 9.5 billion euros ($11.5 billion), are Germany's Uniper and BASF's Wintershall Dea ; Anglo-Dutch oil major Shell; Austria's OMV , and France's Engie.

Comments

Comments are closed.