BR100 Increased By (0.12%)
BR30 Decreased By (-0.06%)
KSE100 Increased By (0.14%)
KSE30 Increased By (0.18%)
BECO 5.63 Decreased By ▼ -0.02 (-0.35%)
BML 65.10 Increased By ▲ 1.22 (1.91%)
BOP 33.63 Decreased By ▼ -0.04 (-0.12%)
CNERGY 8.11 Decreased By ▼ -0.03 (-0.37%)
DCL 11.47 Increased By ▲ 0.09 (0.79%)
FCCL 51.90 Decreased By ▼ -0.37 (-0.71%)
FCSC 5.74 Increased By ▲ 0.24 (4.36%)
FFL 18.00 Increased By ▲ 0.28 (1.58%)
FNEL 1.40 Increased By ▲ 0.09 (6.87%)
HUMNL 11.19 Increased By ▲ 0.01 (0.09%)
KEL 7.86 No Change ▼ 0.00 (0%)
KOSM 5.80 Increased By ▲ 0.16 (2.84%)
MLCF 85.55 Decreased By ▼ -0.05 (-0.06%)
NBP 182.55 Decreased By ▼ -1.07 (-0.58%)
PACE 11.89 Increased By ▲ 0.21 (1.8%)
PAEL 39.95 Decreased By ▼ -0.32 (-0.79%)
PIAHCLA 25.75 Decreased By ▼ -0.05 (-0.19%)
PIBTL 17.08 Increased By ▲ 0.04 (0.23%)
PPL 223.51 Decreased By ▼ -0.55 (-0.25%)
PRL 34.37 Decreased By ▼ -0.25 (-0.72%)
PTC 64.05 Increased By ▲ 0.06 (0.09%)
SEARL 89.70 Decreased By ▼ -0.39 (-0.43%)
SSGC 26.55 Decreased By ▼ -0.05 (-0.19%)
TELE 8.98 Decreased By ▼ -0.10 (-1.1%)
THCCL 68.52 Increased By ▲ 1.16 (1.72%)
TPLP 11.40 Decreased By ▼ -0.02 (-0.18%)
TREET 24.63 Decreased By ▼ -0.08 (-0.32%)
TRG 70.80 Decreased By ▼ -0.18 (-0.25%)
WAVES 11.26 Increased By ▲ 0.28 (2.55%)
WTL 1.28 Increased By ▲ 0.02 (1.59%)

Name of The Project: Tuwairqi Steel Mills Limited( a subsidiary of Al-Tuwairqi Group of Companies, The Kingdom of Saudi Arabia).
2. LOCATION: BIN QASIM, KARACHI
3. CAPACITY:

-- Direct Reduced Iron (DRI)
-- 1.0 million tons per year (MTPY), expandable up to 1.5 MTPY
-- Billets
-- 1.0 MTPY expandable up to 1.5 MPTY
4 LAND: 220 Acres between sea and water intake channel and sea water disposal channel, belonging to Pakistan Steel Mills.
5. RAW MATERIALS:
PHASE-I
-- Iron Oxide Pellets
-- Calibrated Lump Ore
-- Natural Gas
PHASE-II
-- DRI from phase-I
-- Steel Scrap
-- Fluxes
6. PRODUCTS:
-- Direct Reduced Iron (DRI) (Phase-I)
-- Square Billet (Phase-II)
7. TECHNOLOGIES:
PHASE-I
-- Reformed Natural Gas (H2 & CO)
-- Direct Reduction (DR)
PHASE-II
-- Electric Arc Furnace (EAF) and Continuous Casting (CC)
8. TECHNOLOGY SUPPLIES:
PHASE-I
-- MIDREX, USA
PHASE-II
-- VAI Fuchs/Demag/Seimens (Yet to be decided)
9 TARGET MARKET: NEIGHBORING GULF STATES /PAKISTAN
10 ELECTRICITY:

PHASE-I
-- 20-25 MW from own Power Generation
PHASE-II
-- 180 MW from WAPDA / NTDC.(Through own Transmission Line)
11. NATURAL GAS:
-- 40 MMCF per day as Raw Material
-- 5 MMCF per day for Power Generation.
12 POTABLE WATER: 5,000 CM per day will be supplied by Karachi Water & Sewerage Board
13. PORT: Port Muhammad Bin Qasim for Import of raw materials / Export of finished good.
14. SUPPORT FACILITIES:
-- Fabrication Shop.
-- Ready Mix Concrete Batching Plant
15. COMPLETION TARGETS:
PHASE-I
-- September-07
PHASE-II
-- March-09
16 PROJECT COST:
PHASE-I
-- US $130 Million.
PHASE-II
-- US $170 Million.
-- (These Figures are based on the commitment & technical know-how of ATG)
17. DEBT: EQUITY RATIO:
-- 65: 35 (ABN Amro is the lead arranger)
18. STATUS: Plant have Export Processing Zone (EPZ) status.
19. MANPOWER & EMPLOYMENT: Project will provide direct employment to 1,000 persons and an opportunity to another up to 3,500 employments in trade and services related with the main plant.