BR100 Decreased By (-0.25%)
BR30 Decreased By (-0.64%)
KSE100 Decreased By (-0.41%)
KSE30 Decreased By (-0.67%)
BECO 5.83 Decreased By ▼ -0.20 (-3.32%)
BML 57.90 Increased By ▲ 5.15 (9.76%)
BOP 33.79 Decreased By ▼ -0.46 (-1.34%)
CNERGY 8.15 Decreased By ▼ -0.01 (-0.12%)
DCL 11.79 Decreased By ▼ -0.55 (-4.46%)
FCCL 53.49 Decreased By ▼ -0.40 (-0.74%)
FCSC 5.40 Increased By ▲ 0.18 (3.45%)
FFL 17.84 Decreased By ▼ -0.19 (-1.05%)
FNEL 1.30 No Change ▼ 0.00 (0%)
HUMNL 11.11 Increased By ▲ 0.11 (1%)
KEL 8.02 Decreased By ▼ -0.09 (-1.11%)
KOSM 5.45 Increased By ▲ 0.07 (1.3%)
MLCF 87.40 Decreased By ▼ -0.65 (-0.74%)
NBP 184.24 Decreased By ▼ -2.24 (-1.2%)
PACE 11.62 Increased By ▲ 0.90 (8.4%)
PAEL 40.25 Increased By ▲ 0.31 (0.78%)
PIAHCLA 26.12 Decreased By ▼ -0.05 (-0.19%)
PIBTL 17.14 Decreased By ▼ -0.18 (-1.04%)
PPL 228.73 Decreased By ▼ -4.05 (-1.74%)
PRL 34.49 Decreased By ▼ -0.46 (-1.32%)
PTC 67.54 Decreased By ▼ -0.02 (-0.03%)
SEARL 90.93 No Change ▼ 0.00 (0%)
SSGC 26.83 Decreased By ▼ -0.34 (-1.25%)
TELE 8.53 Decreased By ▼ -0.04 (-0.47%)
THCCL 66.14 Increased By ▲ 6.01 (10%)
TPLP 9.33 Increased By ▲ 0.57 (6.51%)
TREET 24.51 Decreased By ▼ -0.03 (-0.12%)
TRG 71.61 Decreased By ▼ -0.14 (-0.2%)
WAVES 10.98 Increased By ▲ 1.00 (10.02%)
WTL 1.28 Increased By ▲ 0.02 (1.59%)
Pakistan

NHA working to expand, upgrade road network in Balochistan

Total cost of the project is Rs22,994 million whereas till June 30, Rs14,914 have been spent. He said Rs1,000
Published October 7, 2019 Updated October 7, 2019 02:27pm
By
  • Total cost of the project is Rs22,994 million whereas till June 30, Rs14,914 have been spent.
  • He said Rs1,000 million have been set aside for dualization and improvement of Yarik-Sagu-Zhob section of N-50 CPEC western alignment out of which Rs100 million have been released.
  • He said Rs5,000 million have been allocated for construction of Hoshab- Khuzdar section of Ratto Dero-Gawadar Motorway.

ISLAMABAD: National Highway Authority (NHA) has been striving to upgrade and expand road infrastructure in Balochistan to bring the providence at par with the developed areas of the country.

Talking to APP, an official of NHA Monday said for construction of two lane highway from Basima to Khuzdar Rs2,000 million have been allocated in Public Sector Development Programme ( PSDP) of 2019-20 fiscal year out of which Rs100 million have been released so far.

The total cost of the project would be Rs19,188 million and till June 30, Rs1,500 million have been spent on the project. Similarly, he said, Rs2,000 million have been allocated under PSDP for widening and strengthening of about 32 kilometers Rakhi- Gajj section of N-70.

Total cost of the project is Rs22,994 million whereas till June 30, Rs14,914 have been spent.

He said Rs1,000 million have been earmarked for construction of black top Yakmach-Kharan road out of which Rs100 million have been issued.

Total estimated cost of the project is Rs13,758 million out of which Rs3,406 million have been spent by end of previous fiscal year.

He said Rs1,000 million have been set aside for dualization and improvement of Yarik-Sagu-Zhob section of N-50 CPEC western alignment out of which Rs100 million have been released.

The total cost of the project is Rs76,488 million and Rs2,972 million expenditure has been occurred by June 30.

He said Rs5,000 million have been allocated for construction of Hoshab- Khuzdar section of Ratto Dero-Gawadar Motorway.

He said for rehabilitation/upgradation and widening of Quetta - Dhadhar Section of N-65 (118.322 km), Rs500 million have been allocated out of which Rs70 million have been issued. For construction of Dera Murad Jamali Bypass Rs 125million have been allocated, he said.