AIRLINK 72.80 Increased By ▲ 0.62 (0.86%)
BOP 5.06 Increased By ▲ 0.13 (2.64%)
CNERGY 4.33 Decreased By ▼ -0.02 (-0.46%)
DFML 30.52 Increased By ▲ 2.03 (7.13%)
DGKC 85.95 Increased By ▲ 4.65 (5.72%)
FCCL 22.35 Increased By ▲ 0.85 (3.95%)
FFBL 33.22 Increased By ▲ 0.17 (0.51%)
FFL 9.78 Decreased By ▼ -0.08 (-0.81%)
GGL 10.40 Decreased By ▼ -0.08 (-0.76%)
HBL 113.62 Decreased By ▼ -0.38 (-0.33%)
HUBC 136.20 Decreased By ▼ -3.80 (-2.71%)
HUMNL 10.03 Increased By ▲ 1.00 (11.07%)
KEL 4.66 Decreased By ▼ -0.07 (-1.48%)
KOSM 4.40 Increased By ▲ 0.02 (0.46%)
MLCF 38.35 Increased By ▲ 0.70 (1.86%)
OGDC 133.40 Decreased By ▼ -0.30 (-0.22%)
PAEL 27.40 Increased By ▲ 1.80 (7.03%)
PIAA 24.76 Increased By ▲ 0.78 (3.25%)
PIBTL 6.55 Increased By ▲ 0.07 (1.08%)
PPL 121.21 Decreased By ▼ -1.41 (-1.15%)
PRL 27.15 Increased By ▲ 0.08 (0.3%)
PTC 13.89 Increased By ▲ 0.29 (2.13%)
SEARL 60.40 Increased By ▲ 3.78 (6.68%)
SNGP 68.53 Decreased By ▼ -0.71 (-1.03%)
SSGC 10.33 Decreased By ▼ -0.01 (-0.1%)
TELE 9.05 Increased By ▲ 0.60 (7.1%)
TPLP 11.26 Decreased By ▼ -0.02 (-0.18%)
TRG 65.70 Increased By ▲ 4.49 (7.34%)
UNITY 25.25 Decreased By ▼ -0.08 (-0.32%)
WTL 1.50 No Change ▼ 0.00 (0%)
BR100 7,608 Decreased By -22.2 (-0.29%)
BR30 25,091 Increased By 100.6 (0.4%)
KSE100 72,658 Increased By 56.2 (0.08%)
KSE30 23,383 Decreased By -155.9 (-0.66%)

Sindh Chief Minister Syed Murad Ali Shah has said he has been working hard to arrange funds and waiting for Nespak report of design verifications on Karachi Bulk Water Supply K-IV project. "I am committed to complete K-IV scheme," he said, presiding over a meeting to review the present status of the project.
The meeting was attended by Minister Local Government Saeed Ghani, Chief Secretary Mumtaz Shah, Secretary Local Government Khalid Hyder Shah, Special Secretary Local Government Niaz Soomro, MD Water Board Asadullah Khan and PD K-IV project Asad Zamin.
The chief minister was told that K-IV was planned for providing 660MDG or 1200 cusecs water to Karachi in three phases. The Phase-I of 260 MGD, Phase-II of another 260 and phase-III of 130 MGD water supply was to be completed between 2022 and 2026.
The phase-I contract was awarded to FWO in 2016 for Rs 28.187 billion that was to be completed in packages within a period of 24 months. The package-A of civil work cost Rs 15.254 billion and package-B of electrical and mechanical works was signed for Rs 12.9 billion.
The K-IV is a three-phased schemes of channels or conduits (conveyance system) only to carry water from Keenjhar (lake) to Karachi. In 2015-16 it was realised that even if K-IV phase-I project was completed, it would not give any benefit to Karachiites because there would not be enough electricity to pump and supply water that meant there was no connectivity of bulk channel with distribution network.-PR