AIRLINK 73.18 Increased By ▲ 0.38 (0.52%)
BOP 5.00 Decreased By ▼ -0.06 (-1.19%)
CNERGY 4.37 Increased By ▲ 0.04 (0.92%)
DFML 29.95 Decreased By ▼ -0.57 (-1.87%)
DGKC 91.39 Increased By ▲ 5.44 (6.33%)
FCCL 23.15 Increased By ▲ 0.80 (3.58%)
FFBL 33.50 Increased By ▲ 0.28 (0.84%)
FFL 9.92 Increased By ▲ 0.14 (1.43%)
GGL 10.35 Decreased By ▼ -0.05 (-0.48%)
HBL 113.01 Decreased By ▼ -0.61 (-0.54%)
HUBC 136.28 Increased By ▲ 0.08 (0.06%)
HUMNL 9.60 Decreased By ▼ -0.43 (-4.29%)
KEL 4.78 Increased By ▲ 0.12 (2.58%)
KOSM 4.72 Increased By ▲ 0.32 (7.27%)
MLCF 39.89 Increased By ▲ 1.54 (4.02%)
OGDC 133.90 Increased By ▲ 0.50 (0.37%)
PAEL 28.85 Increased By ▲ 1.45 (5.29%)
PIAA 25.00 Increased By ▲ 0.24 (0.97%)
PIBTL 6.94 Increased By ▲ 0.39 (5.95%)
PPL 122.40 Increased By ▲ 1.19 (0.98%)
PRL 27.40 Increased By ▲ 0.25 (0.92%)
PTC 14.80 Increased By ▲ 0.91 (6.55%)
SEARL 60.40 No Change ▼ 0.00 (0%)
SNGP 70.29 Increased By ▲ 1.76 (2.57%)
SSGC 10.42 Increased By ▲ 0.09 (0.87%)
TELE 8.85 Decreased By ▼ -0.20 (-2.21%)
TPLP 11.32 Increased By ▲ 0.06 (0.53%)
TRG 66.57 Increased By ▲ 0.87 (1.32%)
UNITY 25.20 Decreased By ▼ -0.05 (-0.2%)
WTL 1.55 Increased By ▲ 0.05 (3.33%)
BR100 7,676 Increased By 42.9 (0.56%)
BR30 25,471 Increased By 298.6 (1.19%)
KSE100 73,086 Increased By 427.5 (0.59%)
KSE30 23,427 Increased By 44.5 (0.19%)
Pakistan

Senate body concerned over delay in capital metro bus extension project

  • The committee chairman said that it was certain that any one of the above mentioned departments was responsible in unnecessary delay in completion of the project.
Published August 20, 2020

ISLAMABAD: The Senate Standing Committee on Planning, Development and Special Initiatives took serious notice over delay in the extension project of metro bus service from New airport Islamabad to Peshawar Morr metro station and said that the delay was causing unnecessary increase in cost of the project.

The meeting of the committee which met here chaired by Senator Agha Shahzaib Durrani decided to take briefing from planning division, ministry of communication and Capital Development Authority on the matter in its next meeting.

The committee chairman said that it was certain that any one of the above mentioned departments was responsible in unnecessary delay in completion of the project.

He said after the briefing, the committee would form a sub-committee to probe in to the matter so that the responsible individuals or departments should be identified.

The committee members also expressed concern over the delay in the project saying that ownership of the project had not been decided yet that might cause operational issues after completion.

The CDA authorities informed the committee that National Highway Authority was assigned the responsibility of the project and the total cost of the 25.6 long metro bus project was estimated at Rs. 16.4 billion.

The meeting was informed that the infrastructure of the project would be completed by next month however more time was needed to make it fully functional as other services works of the project was still pending.

It was further informed that draft legislation for setting up Capital Mass Transit Authority and the private sector would have opportunities of investment in this sector.

The meeting was also attended by Senators Hidayat Ullah, Fida Muhamamd, Rana Maqbool Ahmed, Asad Ashraf and Engineer Rukhsana Bukhari besides Secretary Planning and other high officials of the concerned departments.