BR100 Increased By (0.02%)
BR30 Increased By (0.06%)
KSE100 Decreased By (-0%)
KSE30 Increased By (0.05%)
BECO 5.52 Decreased By ▼ -0.02 (-0.36%)
BML 56.70 Decreased By ▼ -0.39 (-0.68%)
BOP 35.20 Decreased By ▼ -0.01 (-0.03%)
CNERGY 8.15 Decreased By ▼ -0.05 (-0.61%)
DCL 11.61 Decreased By ▼ -0.03 (-0.26%)
FCCL 56.61 Increased By ▲ 0.12 (0.21%)
FCSC 5.38 Increased By ▲ 0.06 (1.13%)
FFL 17.95 Decreased By ▼ -0.11 (-0.61%)
FNEL 1.29 No Change ▼ 0.00 (0%)
HUMNL 11.10 Decreased By ▼ -0.09 (-0.8%)
KEL 8.39 Increased By ▲ 0.19 (2.32%)
KOSM 6.63 Decreased By ▼ -0.04 (-0.6%)
MLCF 101.06 Increased By ▲ 0.30 (0.3%)
NBP 202.44 Decreased By ▼ -0.56 (-0.28%)
PACE 11.42 Decreased By ▼ -0.07 (-0.61%)
PAEL 43.32 Increased By ▲ 0.24 (0.56%)
PIAHCLA 27.24 Increased By ▲ 0.24 (0.89%)
PIBTL 17.82 Decreased By ▼ -0.02 (-0.11%)
PPL 244.79 Increased By ▲ 2.16 (0.89%)
PRL 35.71 Decreased By ▼ -0.16 (-0.45%)
PTC 65.45 Decreased By ▼ -0.40 (-0.61%)
SEARL 93.55 Decreased By ▼ -0.03 (-0.03%)
SSGC 32.98 Increased By ▲ 0.75 (2.33%)
TELE 9.04 Decreased By ▼ -0.07 (-0.77%)
THCCL 66.80 Increased By ▲ 0.31 (0.47%)
TPLP 10.85 Decreased By ▼ -0.10 (-0.91%)
TREET 25.48 Decreased By ▼ -0.24 (-0.93%)
TRG 65.90 Decreased By ▼ -0.05 (-0.08%)
WAVES 11.13 Decreased By ▼ -0.03 (-0.27%)
WTL 1.27 Increased By ▲ 0.01 (0.79%)

ISLAMABAD: Pakistan is poised to save USD 3.239 billion over the next 26 years — USD 2.113 billion in foreign currency alone — by converting the Jamshoro Unit-01 power plant from imported coal to 100 percent indigenous Thar lignite.

According to Power Division, a world-class Bankable Feasibility Study (BFS), prepared by Dornier Group and EY Parthenon and presented today to Federal Minister for Power Sardar Awais Ahmed Khan Leghari, confirms that this transformation is not only technically feasible and economically compelling but also environmentally manageable.

The achievement of this milestone was made possible through the active support and collaboration of key stakeholders, including K-Electric (KE), Jamshoro Power Company Limited (JPCL), and the Private Power and Infrastructure Board (PPIB). To steer this complex initiative, the Federal Minister constituted a high-level steering committee, which convened 38 dedicated sessions to proactively monitor and expedite the completion of the BFS. Of these, 15 sessions were personally chaired by the Minister, reflecting the Government’s unwavering commitment to this transformative project. The Minister has expressed his sincere gratitude to KE, JPCL, PPIB, and all other partners for their invaluable support in bringing this feasibility study to fruition.

The initiative flows directly from the Prime Minister’s Power Sector Reform Plan and reflects sustained efforts by the Ministry of Energy to advance fuel indigenisation, with the BFS marking a key milestone in that process.

The economic case for the conversion is exceptionally strong. The project delivers a cost-benefit ratio of 1.8x, which remains favourable across all sensitivity scenarios. Total net benefits over the 26-year project life amount to USD 3.239 billion, comprising USD 1.720 billion in net benefits to the power sector, including generation cost savings of USD 1.051 billion and Thar mine expansion benefits of USD 669 million — alongside USD 1.519 billion in government savings from reduced interest costs on foreign borrowings. Critically, the project generates USD 2.113 billion in foreign currency savings, directly strengthening Pakistan’s balance of payments and reducing exposure to volatile international coal prices and exchange rate fluctuations. The required conversion CAPEX is estimated at USD 86.2 million (with total project cost of USD 116.6 million), representing a highly attractive return on investment.

The BFS, prepared by the internationally renowned Dornier Group as lead technical consultant, confirms that Jamshoro Unit-01 — Pakistan’s ultra-supercritical power plant — can be converted to burn 100 percent Thar lignite through targeted engineering modifications rather than a large-scale boiler retrofit, thereby preserving the value of the existing plant asset. The project is structured as a bankability-led brown-field modification, with a stage-gate implementation approach that introduces no new coal capacity.

Beyond the direct financial savings, the conversion carries transformative economic co-benefits for Pakistan. The shift to Thar lignite will catalyse the expansion of coal mines in Tharparkar, generating employment, accelerating infrastructure development in one of Pakistan’s most underserved regions, and deepening the country’s domestic energy supply chain. By eliminating reliance on imported coal — subject to international commodity price fluctuations, foreign exchange volatility, and supply chain disruptions — Pakistan will move decisively towards energy self-sufficiency, consistent with the Government’s broader indigenisation agenda under the Power Sector Reform Plan.

With the BFS now formally presented, the Ministry of Energy (Power Division) will proceed to the implementation readiness phase. Immediate next steps include obtaining final policy approval, initiating the lender-consent work stream and loan amendment roadmap, preparing the NEPRA/TCEB/SEPA/PPRA/PPA/CSA/EPC consent and contract matrix, launching basic design tender verification — including CFD modelling, mill tests, FGD/ESP and balance-of-plant modifications, and HAZIG/HAZOP studies — and developing a comprehensive procurement and contracting strategy with appropriate interface allocation and guarantees.