BR100 Increased By (1.02%)
BR30 Increased By (1.71%)
KSE100 Increased By (0.58%)
KSE30 Increased By (0.65%)
BECO 6.03 Increased By ▲ 0.26 (4.51%)
BML 52.61 Decreased By ▼ -0.39 (-0.74%)
BOP 34.23 Increased By ▲ 0.24 (0.71%)
CNERGY 8.16 Increased By ▲ 0.05 (0.62%)
DCL 12.23 Increased By ▲ 0.03 (0.25%)
FCCL 53.80 Increased By ▲ 0.97 (1.84%)
FCSC 5.24 Increased By ▲ 0.17 (3.35%)
FFL 18.03 Increased By ▲ 0.08 (0.45%)
FNEL 1.30 Increased By ▲ 0.01 (0.78%)
HUMNL 11.00 Increased By ▲ 0.12 (1.1%)
KEL 8.07 Increased By ▲ 0.05 (0.62%)
KOSM 5.39 Decreased By ▼ -0.13 (-2.36%)
MLCF 87.90 Increased By ▲ 1.39 (1.61%)
NBP 186.60 Increased By ▲ 1.44 (0.78%)
PACE 10.75 Increased By ▲ 0.17 (1.61%)
PAEL 39.95 Increased By ▲ 0.53 (1.34%)
PIAHCLA 26.19 Decreased By ▼ -0.03 (-0.11%)
PIBTL 17.32 Increased By ▲ 0.65 (3.9%)
PPL 233.49 Increased By ▲ 5.31 (2.33%)
PRL 34.98 Increased By ▲ 0.30 (0.87%)
PTC 67.71 Increased By ▲ 2.38 (3.64%)
SEARL 90.90 Increased By ▲ 0.77 (0.85%)
SSGC 27.20 Increased By ▲ 0.60 (2.26%)
TELE 8.57 Increased By ▲ 0.29 (3.5%)
THCCL 60.85 Increased By ▲ 2.35 (4.02%)
TPLP 8.78 Increased By ▲ 0.56 (6.81%)
TREET 24.65 Increased By ▲ 0.12 (0.49%)
TRG 71.50 Increased By ▲ 1.79 (2.57%)
WAVES 10.01 Increased By ▲ 0.07 (0.7%)
WTL 1.27 Decreased By ▼ -0.01 (-0.78%)

ISLAMABAD: The World Bank “Punjab Human Capital Investment Project (PHCIP)” worth $200 million made limited progress in the implementation of the components on social protection, education, and health.

The bank has rated the progress towards achievement of the PDO and overall implementation progress as moderately unsatisfactory, while the overall project risk rating as substantial.

The bank documents revealed that the project development objective was to increase the utilization of quality health services, and economic and social inclusion programmes, among poor and vulnerable households in select districts in Punjab.

PLUS project discussed with World Bank representatives

The project components included health services quality and utilisation (cost $115 million), economic and social inclusion (cost $65 million), and efficiency and sustainability through social protection services delivery system and project management (cost $20 million).

The project made limited progress in the implementation of the components on social protection, education and health. Key activities in progress include the upgradation of healthcare facilities; renovation of ECE classrooms; beneficiary registration for the Health CCT and Economic Inclusion (EI) component; and cash and asset disbursement to the registered beneficiaries. Overall disbursement and expenditure remain low due to delays in procurement, limited social mobilisation, and challenges of timely payments to the beneficiaries.

Actions to expedite include completion of key procurements by March 15, 2023; improvement in the cash disbursements mechanism; and the introduction of a predictable and enhanced monthly payment have been agreed with the Government of Punjab, documents noted.

The sponsoring agency of the PHCIP is the government of Punjab through the World Bank -International Development Agency and in-kind counterpart funding. The signing, as well as the effectiveness date of the project, is 18th May 2020, whereas, the closing date of the loan agreement is 30th June 2025.

The total cost of the approved project is $330 million where $200 million will be provided by World Bank and $130 million from counterpart funding.

The spread of the Punjab Human Capital Investment Project (PHCIP) is over 11 Districts of Punjab including Muzaffargarh, Bahawalpur, Rajanpur, DG Khan, Rahim Yar Khan, Bhakkar, Mianwali, Bahawalnagar, Lodhran, Layyah, and Khushab. The implementing partners of the projects are Punjab Social Protection Authority (PSPA), the Primary and Secondary Health Department (PSHD), and Punjab School Education Department (SED). The gestation period of the project is from 2021 till 2025 and the lead agency for the PaHCIP is the PSPA.

Copyright Business Recorder, 2023

Comments

Comments are closed for this article.

Tulukan Mairandi Mar 12, 2023 03:47pm
The report also states that 16 Toyota Land Cruisers and 4 Honda CRVs were purchased for "surveys". So far $128 million has been spent with no results.