BR100 Decreased By (-0.25%)
BR30 Decreased By (-0.64%)
KSE100 Decreased By (-0.41%)
KSE30 Decreased By (-0.67%)
BECO 5.83 Decreased By ▼ -0.20 (-3.32%)
BML 57.90 Increased By ▲ 5.15 (9.76%)
BOP 33.79 Decreased By ▼ -0.46 (-1.34%)
CNERGY 8.15 Decreased By ▼ -0.01 (-0.12%)
DCL 11.79 Decreased By ▼ -0.55 (-4.46%)
FCCL 53.49 Decreased By ▼ -0.40 (-0.74%)
FCSC 5.40 Increased By ▲ 0.18 (3.45%)
FFL 17.84 Decreased By ▼ -0.19 (-1.05%)
FNEL 1.30 No Change ▼ 0.00 (0%)
HUMNL 11.11 Increased By ▲ 0.11 (1%)
KEL 8.02 Decreased By ▼ -0.09 (-1.11%)
KOSM 5.45 Increased By ▲ 0.07 (1.3%)
MLCF 87.40 Decreased By ▼ -0.65 (-0.74%)
NBP 184.24 Decreased By ▼ -2.24 (-1.2%)
PACE 11.62 Increased By ▲ 0.90 (8.4%)
PAEL 40.25 Increased By ▲ 0.31 (0.78%)
PIAHCLA 26.12 Decreased By ▼ -0.05 (-0.19%)
PIBTL 17.14 Decreased By ▼ -0.18 (-1.04%)
PPL 228.73 Decreased By ▼ -4.05 (-1.74%)
PRL 34.49 Decreased By ▼ -0.46 (-1.32%)
PTC 67.54 Decreased By ▼ -0.02 (-0.03%)
SEARL 90.93 No Change ▼ 0.00 (0%)
SSGC 26.83 Decreased By ▼ -0.34 (-1.25%)
TELE 8.53 Decreased By ▼ -0.04 (-0.47%)
THCCL 66.14 Increased By ▲ 6.01 (10%)
TPLP 9.33 Increased By ▲ 0.57 (6.51%)
TREET 24.51 Decreased By ▼ -0.03 (-0.12%)
TRG 71.61 Decreased By ▼ -0.14 (-0.2%)
WAVES 10.98 Increased By ▲ 1.00 (10.02%)
WTL 1.28 Increased By ▲ 0.02 (1.59%)
Pakistan

1st unit of Tarbela 4th extension project to start generation on Feb 25

ISLAMABAD: As many as 91.88 per cent work has been completed on the Tarbela 4th Extension Power Project so far and i
Published January 10, 2018 Updated January 10, 2018 02:18pm

ISLAMABAD: As many as 91.88 per cent work has been completed on the Tarbela 4th Extension Power Project so far and its first unit (470 MW) will start generation on February 25, 2018.

Talking to APP, Project Director of Tarbela 4th Extension Power Project Shoail Khan said, “over all physical work on the project has reached at 91.88 per cent so far.” Dry testing would be conducted on January 25 while wet testing would start on January 26, he said.    He said the 2nd unit (470 MW) would start generation by April 25, followed by third unit (470 MW) on May 30, he said.

He said the project would cost $ 920 million and additional 1410 MW cheaper hydel electricity would be generated.

Sohail Khan said the World Bank had provided $ 840 million for the project while Water and Power Development Authority arranged the remaining $ 80 million.

He said three units of 470 MW each were being installed at the power house which would enhance the total electricity generation to 4888 MW from the existing 3478 MW.

Dilating upon the benefits of the project, he said the project having three units of 470MW each would produce 3,840GWh of cheap hydropower at a time when electricity needs would be at peak in hot and humid weather.

Annual benefits of the project have been estimated at around Rs30.7 billion. The project will pay back its cost in just three years.

Copyright APP (Associated Press of Pakistan), 2018