BR100 Increased By (0.99%)
BR30 Increased By (0.38%)
KSE100 Increased By (1.06%)
KSE30 Increased By (1.14%)
BECO 5.39 Increased By ▲ 0.07 (1.32%)
BML 56.48 Increased By ▲ 1.39 (2.52%)
BOP 35.09 Increased By ▲ 0.05 (0.14%)
CNERGY 8.17 Increased By ▲ 0.08 (0.99%)
DCL 11.44 Increased By ▲ 0.08 (0.7%)
FCCL 57.55 Increased By ▲ 1.36 (2.42%)
FCSC 5.00 Decreased By ▼ -0.01 (-0.2%)
FFL 17.88 Increased By ▲ 0.20 (1.13%)
FNEL 1.25 Increased By ▲ 0.01 (0.81%)
HUMNL 11.17 Increased By ▲ 0.24 (2.2%)
KEL 8.54 Decreased By ▼ -0.03 (-0.35%)
KOSM 6.73 Increased By ▲ 0.24 (3.7%)
MLCF 106.91 Increased By ▲ 0.40 (0.38%)
NBP 198.50 Decreased By ▼ -1.26 (-0.63%)
PACE 11.07 Increased By ▲ 0.05 (0.45%)
PAEL 45.45 Increased By ▲ 0.45 (1%)
PIAHCLA 31.43 Increased By ▲ 2.86 (10.01%)
PIBTL 19.08 Increased By ▲ 0.81 (4.43%)
PPL 242.62 Decreased By ▼ -1.87 (-0.76%)
PRL 35.67 Increased By ▲ 0.73 (2.09%)
PTC 65.52 Decreased By ▼ -0.30 (-0.46%)
SEARL 94.54 Increased By ▲ 0.49 (0.52%)
SSGC 32.08 Increased By ▲ 1.25 (4.05%)
TELE 8.87 Increased By ▲ 0.17 (1.95%)
THCCL 65.66 Increased By ▲ 0.67 (1.03%)
TPLP 10.73 Increased By ▲ 0.47 (4.58%)
TREET 25.11 Increased By ▲ 0.24 (0.97%)
TRG 63.67 Increased By ▲ 0.31 (0.49%)
WAVES 10.70 Increased By ▲ 0.05 (0.47%)
WTL 1.25 Increased By ▲ 0.01 (0.81%)

LAHORE: A full-scale Roller Compacted Concrete (RCC) trial has commenced on the Dasu Hydropower Project which is a pre-requisite to lay RCC for main dam of the project.

A team of engineers and technical experts is conducting the full-scale RCC placement at a dedicated trial section located near the main dam site with the purpose to validate construction methodologies, ensure consistent quality standards, assess logistical and operational systems, identify potential technical challenges, and provide practical training to the project’s workforce.

The full-scale trial, including its testing, is expected to be completed in 4 months, a statement issued by WAPDA headquarters said.

Teams from the contractor, the consultants, and WAPDA will review and evaluate all technical aspects of the trial before formal commencement of RCC works at the main dam, scheduled later this year, depending upon the availability of pozzolan from Gini area, which despite efforts spread over a decade, WAPDA has not been able to acquire.