BR100 Increased By (0.36%)
BR30 Decreased By (-0.13%)
KSE100 Increased By (0.22%)
KSE30 Increased By (0.37%)
AGHA 6.68 Increased By ▲ 0.01 (0.15%)
BECO 4.37 No Change ▼ 0.00 (0%)
BML 57.32 Increased By ▲ 0.88 (1.56%)
BOP 30.35 Increased By ▲ 0.01 (0.03%)
CNERGY 13.12 Increased By ▲ 0.03 (0.23%)
CSIL 5.41 Increased By ▲ 0.05 (0.93%)
FCCL 52.79 Increased By ▲ 0.41 (0.78%)
FFL 14.72 Decreased By ▼ -0.02 (-0.14%)
FNEL 1.12 No Change ▼ 0.00 (0%)
KEL 6.09 No Change ▼ 0.00 (0%)
KOSM 5.73 Increased By ▲ 0.77 (15.52%)
LOTCHEM 26.46 Decreased By ▼ -0.89 (-3.25%)
MLCF 93.16 Increased By ▲ 0.41 (0.44%)
NBP 164.66 Decreased By ▼ -0.32 (-0.19%)
NCPL 55.66 Increased By ▲ 0.02 (0.04%)
NPL 61.16 Decreased By ▼ -0.10 (-0.16%)
OGDC 316.73 Decreased By ▼ -1.03 (-0.32%)
PACE 9.87 Decreased By ▼ -0.06 (-0.6%)
PAEL 35.63 Increased By ▲ 0.13 (0.37%)
PIBTL 14.68 Increased By ▲ 0.11 (0.75%)
PPL 226.91 Decreased By ▼ -0.88 (-0.39%)
PRL 93.02 Increased By ▲ 0.45 (0.49%)
PTC 60.26 Decreased By ▼ -0.37 (-0.61%)
SSGC 23.81 Increased By ▲ 0.01 (0.04%)
TBL 8.75 Increased By ▲ 0.07 (0.81%)
TELE 7.80 Increased By ▲ 0.02 (0.26%)
TPL 22.35 Increased By ▲ 0.12 (0.54%)
TPLP 12.97 Increased By ▲ 0.30 (2.37%)
TREET 22.16 Decreased By ▼ -0.38 (-1.69%)
TRG 56.56 Decreased By ▼ -1.24 (-2.15%)
Print Print edition: 2026-05-14

Nepra rejects NGC’s review plea against CPPA-G

Published Updated

ISLAMABAD: The National Electric Power Regulatory Authority (NEPRA) has rejected a review petition filed by the National Grid Company (NGC) against its earlier determination regarding the registration of Central Power Purchasing Agency (Guarantee) Limited (CPPA-G) as a Special Purpose Agent (SPA) and approval of the Agency Code, reaffirming the transition toward a competitive electricity market.

According to NEPRA’s detailed decision issued on May 13, 2026, the Authority found no merit in the grounds raised by NGC, stating that the petition neither identified any error apparent on record nor presented new or material evidence required under the NEPRA (Review Procedure) Regulations, 2009.

NGC had challenged key aspects of the Agency Code, particularly the shift from centralised billing and settlement through CPPA-G to a direct, bilateral contractual framework.

The company also sought continuation of the existing mechanism for recovery of Use of Transmission System Charges (UoTSC) and Pak Matiari-Lahore Transmission Company (PMLTC) charges.

However, NEPRA ruled that such requests were inconsistent with the Competitive Trading Bilateral Contract Market (CTBCM) framework, which mandates direct billing, settlement, and recovery arrangements between market participants. The Authority emphasized that the move away from centralized pooling is essential to improve financial discipline, transparency, and accountability in the power sector.

On the issue of PMLTC charges, the Authority rejected NGC’s claim that these should be treated as legacy pass-through liabilities. It clarified that only Power Purchase Agreements (PPAs) and Energy Purchase Agreements (EPAs) fall under the definition of legacy contracts, and transmission-related obligations do not qualify.

NEPRA also dismissed NGC’s concerns regarding increased payment risks under direct billing, noting that centralized mechanisms merely redistribute risks rather than eliminate them. The Authority maintained that under the new market structure, each entity must assume responsibility for its receivables and adopt appropriate contractual safeguards. The regulator further rejected proposals to introduce a “pay first, dispute later” principle, extend delayed payment surcharge provisions to transmission charges, and grant priority payment status to NGC.