AIRLINK 69.92 Increased By ▲ 4.72 (7.24%)
BOP 5.46 Decreased By ▼ -0.11 (-1.97%)
CNERGY 4.50 Decreased By ▼ -0.06 (-1.32%)
DFML 25.71 Increased By ▲ 1.19 (4.85%)
DGKC 69.85 Decreased By ▼ -0.11 (-0.16%)
FCCL 20.02 Decreased By ▼ -0.28 (-1.38%)
FFBL 30.69 Increased By ▲ 1.58 (5.43%)
FFL 9.75 Decreased By ▼ -0.08 (-0.81%)
GGL 10.12 Increased By ▲ 0.11 (1.1%)
HBL 114.90 Increased By ▲ 0.65 (0.57%)
HUBC 132.10 Increased By ▲ 3.00 (2.32%)
HUMNL 6.73 Increased By ▲ 0.02 (0.3%)
KEL 4.44 No Change ▼ 0.00 (0%)
KOSM 4.93 Increased By ▲ 0.04 (0.82%)
MLCF 36.45 Decreased By ▼ -0.55 (-1.49%)
OGDC 133.90 Increased By ▲ 1.60 (1.21%)
PAEL 22.50 Decreased By ▼ -0.04 (-0.18%)
PIAA 25.39 Decreased By ▼ -0.50 (-1.93%)
PIBTL 6.61 Increased By ▲ 0.01 (0.15%)
PPL 113.20 Increased By ▲ 0.35 (0.31%)
PRL 30.12 Increased By ▲ 0.71 (2.41%)
PTC 14.70 Decreased By ▼ -0.54 (-3.54%)
SEARL 57.55 Increased By ▲ 0.52 (0.91%)
SNGP 66.60 Increased By ▲ 0.15 (0.23%)
SSGC 10.99 Increased By ▲ 0.01 (0.09%)
TELE 8.77 Decreased By ▼ -0.03 (-0.34%)
TPLP 11.51 Decreased By ▼ -0.19 (-1.62%)
TRG 68.61 Decreased By ▼ -0.01 (-0.01%)
UNITY 23.47 Increased By ▲ 0.07 (0.3%)
WTL 1.34 Decreased By ▼ -0.04 (-2.9%)
BR100 7,399 Increased By 104.2 (1.43%)
BR30 24,136 Increased By 282 (1.18%)
KSE100 70,910 Increased By 619.8 (0.88%)
KSE30 23,377 Increased By 205.6 (0.89%)

SINGAPORE /ASHGABAT: China is accelerating the building of a long-delayed Central Asian pipeline to source gas from Turkmenistan even as Russia pushes its own new Siberian connection, as Beijing juggles its energy security needs with diplomatic priorities.

Beijing is keen to bolster Central Asia ties under its Belt & Road Initiative, but nearly a decade after construction began, the “Line D” project has been hobbled by complex price talks and the technical hurdles of laying a pipeline crossing another three central Asian nations, Chinese state oil officials said.

But Moscow’s recent push to land its second Siberia pipeline connection with China, the Power of Siberia 2, to make up for shrunken sales in Europe due to the Ukraine crisis, provides Beijing a lever to advance the central Asian project, according to Chinese oil officials and industry consultants.

“Central Asian pipelines are considered a cornerstone investment in China’s energy and geopolitical space. It’s a supply channel with strategic value that supersedes commercial concerns,” a state-oil official familiar with China National Petroleum Corp’s (CNPC) global strategy told Reuters.

China may eventually seal both deals to feed its massive long-term gas needs, but is prioritising Turkmenistan, industry officials said, as Beijing has long seen Central Asia as a frontier to expand trade, secure energy and maintain stability in its once-restive western Xinjiang region.

Combined, multi-year contracts worth tens of billions of dollars to bring gas via both pipelines would meet 20% of China’s current demand. The pipelines are key to Beijing’s goal of using gas as a bridge fuel towards its carbon neutrality targets and also helping to shield it from the volatile tanker-carried liquefied natural gas (LNG) market.

Estimated in 2014 to cost $6.7 billion, Line D would carry 30 billion cubic meters of gas a year.

Speaking last week at the first in-person summit of central Asian leaders in the ancient Silk Road city of Xian, President Xi Jinping urged parties to accelerate laying Line D, which would be China’s fourth gas pipeline to the region, almost a decade after the start of construction in Tajikistan.

In 2022, China imported 35 bcm gas or worth $10.3 billion via three pipelines from Turkmenistan, compared with 16 bcm via a single pipeline from Russia at about $4 billion.

Reflecting renewed urgency, CNPC last week launched the feasibility study for a 200-kilometer connection from Xinjiang’s border with Kyrgyzstan to the Chinese town of Wuqia as the first receiving point, said a senior source involved in appraising the project.

“This means D Line is getting ready,” the person told Reuters, adding that construction on the domestic trunkline in Xinjiang could begin next year.

Separately, a CNPC official told Reuters last week that the company’s commercial teams are “standing by” awaiting a mandate to advance the project, without elaborating.

Without a final gas supply contract, CNPC has only built part of the first tunnel in the mountainous Tajikistan capital Dushanbe where Line D begins, the official said.

China’s state planner the National Development and Reform Commission did not immediately respond to a request for comment.