AIRLINK 69.20 Decreased By ▼ -3.86 (-5.28%)
BOP 4.90 Decreased By ▼ -0.19 (-3.73%)
CNERGY 4.26 Decreased By ▼ -0.11 (-2.52%)
DFML 31.25 Decreased By ▼ -1.20 (-3.7%)
DGKC 77.25 Increased By ▲ 1.76 (2.33%)
FCCL 20.00 Increased By ▲ 0.48 (2.46%)
FFBL 35.00 Decreased By ▼ -1.15 (-3.18%)
FFL 9.12 Decreased By ▼ -0.10 (-1.08%)
GGL 9.80 Decreased By ▼ -0.05 (-0.51%)
HBL 112.76 Decreased By ▼ -3.94 (-3.38%)
HUBC 133.04 Increased By ▲ 0.35 (0.26%)
HUMNL 6.95 Decreased By ▼ -0.15 (-2.11%)
KEL 4.23 Decreased By ▼ -0.18 (-4.08%)
KOSM 4.25 Decreased By ▼ -0.15 (-3.41%)
MLCF 36.60 Increased By ▲ 0.40 (1.1%)
OGDC 132.87 Decreased By ▼ -0.63 (-0.47%)
PAEL 22.64 Increased By ▲ 0.04 (0.18%)
PIAA 24.20 Decreased By ▼ -1.81 (-6.96%)
PIBTL 6.46 Decreased By ▼ -0.09 (-1.37%)
PPL 116.30 Increased By ▲ 0.99 (0.86%)
PRL 25.90 Decreased By ▼ -0.73 (-2.74%)
PTC 13.08 Decreased By ▼ -1.02 (-7.23%)
SEARL 52.00 Decreased By ▼ -1.45 (-2.71%)
SNGP 67.60 Increased By ▲ 0.35 (0.52%)
SSGC 10.54 Decreased By ▼ -0.16 (-1.5%)
TELE 8.28 Decreased By ▼ -0.14 (-1.66%)
TPLP 10.80 Increased By ▲ 0.05 (0.47%)
TRG 59.29 Decreased By ▼ -4.58 (-7.17%)
UNITY 25.13 Increased By ▲ 0.01 (0.04%)
WTL 1.27 No Change ▼ 0.00 (0%)
BR100 7,409 Decreased By -52.4 (-0.7%)
BR30 24,036 Decreased By -134.9 (-0.56%)
KSE100 70,667 Decreased By -435.6 (-0.61%)
KSE30 23,224 Decreased By -170.8 (-0.73%)

TEGALLUAR, (Indonesia): A high-speed railway project in Indonesia, part of China’s Belt and Road Initiative, is on track for a 2023 launch despite ongoing negotiations between the two countries about the project being over-budget, officials said on Thursday.

President Joko Widodo inspected a new train station, where the consortium building the railway, PT KCIC, displayed a stationary China-made bullet train on the tracks. The 142-km line will connect the capital Jakarta with one of the country’s largest cities, Bandung.

“This will be the first high-speed rail in ASEAN and we hope this will increase connectivity between countries, whether this (the railway) will be connected further to an airport or other high-speed railways,” he said, referring to the Association of South East Asian Nations.

Jokowi, as the president is popularly known, said the project was 88.8% complete and its commercial launch is expected in June, 2023.

KCIC has said the project is facing a cost overrun of about $2 billion, raising the estimated total cost to 113 trillion rupiah ($7.36 billion). China estimates the project is less than $1 billion over budget, according to Koran Tempo newspaper.

KCIC’s President Director Dwiyana Slamet Riyadi confirmed the discrepancy in cost calculations, saying negotiations are underway to resolve it.

“We hope the negotiations...regarding cost overrun and financing can be quick so this does not disturb the progress,” said Dwiyana, who accompanied Jokowi on Thursday.