BR100 Decreased By (-0.91%)
BR30 Decreased By (-1.47%)
KSE100 Decreased By (-0.78%)
KSE30 Decreased By (-0.75%)
AGHA 6.70 Increased By ▲ 0.02 (0.3%)
BECO 4.37 No Change ▼ 0.00 (0%)
BML 56.00 Decreased By ▼ -1.32 (-2.3%)
BOP 30.09 Decreased By ▼ -0.26 (-0.86%)
CNERGY 12.95 Decreased By ▼ -0.17 (-1.3%)
CSIL 5.33 Decreased By ▼ -0.08 (-1.48%)
FCCL 51.50 Decreased By ▼ -1.29 (-2.44%)
FFL 14.47 Decreased By ▼ -0.25 (-1.7%)
FNEL 1.22 Increased By ▲ 0.10 (8.93%)
KEL 6.03 Decreased By ▼ -0.06 (-0.99%)
KOSM 5.84 Increased By ▲ 0.11 (1.92%)
LOTCHEM 26.20 Decreased By ▼ -0.26 (-0.98%)
MLCF 91.00 Decreased By ▼ -2.16 (-2.32%)
NBP 164.00 Decreased By ▼ -0.66 (-0.4%)
NCPL 53.00 Decreased By ▼ -2.66 (-4.78%)
NPL 59.40 Decreased By ▼ -1.76 (-2.88%)
OGDC 313.67 Decreased By ▼ -3.06 (-0.97%)
PACE 9.72 Decreased By ▼ -0.15 (-1.52%)
PAEL 35.27 Decreased By ▼ -0.36 (-1.01%)
PIBTL 14.71 Increased By ▲ 0.03 (0.2%)
PPL 221.18 Decreased By ▼ -5.73 (-2.53%)
PRL 90.91 Decreased By ▼ -2.11 (-2.27%)
PTC 58.53 Decreased By ▼ -1.73 (-2.87%)
SSGC 23.30 Decreased By ▼ -0.51 (-2.14%)
TBL 8.78 Increased By ▲ 0.03 (0.34%)
TELE 7.60 Decreased By ▼ -0.20 (-2.56%)
TPL 22.03 Decreased By ▼ -0.32 (-1.43%)
TPLP 12.60 Decreased By ▼ -0.37 (-2.85%)
TREET 21.77 Decreased By ▼ -0.39 (-1.76%)
TRG 55.91 Decreased By ▼ -0.65 (-1.15%)

ISLAMABAD: China Power Hub Generation Company (Pvt) Ltd (CPHGCL) has urged Central Power Purchasing Agency Guaranteed (CPPA-G) to resolve the issues of revolving account and foreign currency saying that two payments awaiting the SBP approval has resulted in exchange loss of Rs 1.3 billion.

M/s CPHGCL is a 2x660 MW coal-fired power plant and a dedicated coal import jetty located in Hub (Balochistan). The $ 2 billion IPP is a priority CPEC project that is supplying reliable electricity to millions of Pakistani households.

The company’s Chief Executive Officer (CEO) and Chief Financial Officers (CFO) have written letters to different top government officials where the issues being faced by the power company have been brought to their notice.

According to the CFO, with reference to Revolving Account Agreement, CPPA-G is required to establish the revolving account within 30 days of COD (August 17, 2019). However, till date, no such account has been established in compliance with the agreement.

Non-availability of forex: CPHGC lands in hot water as SBP stops payments

CPHGCL says that it has conveyed its concerns in 12 different letters and meetings with relevant officials of Government of Pakistan and CPPA-G.

A joint meeting was held between all CPEC projects & CFO of CPPA-G, Rehan Akhtar (incumbent CEO) in February, 2022, wherein the CFO (CPPA-G) clarified that the CPPA-G is in the process of negotiation with banks to establish working capital lines and that the revolving account will be maintained for invoices submitted after the availability of working capital lines by CPPAG. No fund will be maintained for the existing overdue invoices.

Copyright Business Recorder, 2022