AGL 40.01 Increased By ▲ 1.23 (3.17%)
AIRLINK 197.85 Increased By ▲ 3.56 (1.83%)
BOP 10.37 Decreased By ▼ -0.47 (-4.34%)
CNERGY 7.13 Increased By ▲ 0.26 (3.78%)
DCL 10.61 Increased By ▲ 0.42 (4.12%)
DFML 43.82 Increased By ▲ 0.69 (1.6%)
DGKC 105.67 Increased By ▲ 9.06 (9.38%)
FCCL 39.60 Increased By ▲ 1.53 (4.02%)
FFBL 80.25 Decreased By ▼ -1.18 (-1.45%)
FFL 14.14 Increased By ▲ 0.11 (0.78%)
HUBC 120.56 Increased By ▲ 1.58 (1.33%)
HUMNL 14.67 Decreased By ▼ -0.10 (-0.68%)
KEL 6.16 Increased By ▲ 0.42 (7.32%)
KOSM 8.26 Decreased By ▼ -0.23 (-2.71%)
MLCF 49.61 Increased By ▲ 3.07 (6.6%)
NBP 74.48 Decreased By ▼ -2.75 (-3.56%)
OGDC 197.07 Increased By ▲ 2.29 (1.18%)
PAEL 35.10 Increased By ▲ 0.36 (1.04%)
PIBTL 8.52 Increased By ▲ 0.14 (1.67%)
PPL 176.26 Increased By ▲ 1.69 (0.97%)
PRL 33.26 Increased By ▲ 0.09 (0.27%)
PTC 25.59 Increased By ▲ 1.02 (4.15%)
SEARL 121.04 Increased By ▲ 11.00 (10%)
TELE 9.90 Increased By ▲ 1.00 (11.24%)
TOMCL 35.23 Increased By ▲ 0.40 (1.15%)
TPLP 12.74 Increased By ▲ 1.05 (8.98%)
TREET 18.97 Increased By ▲ 0.41 (2.21%)
TRG 60.28 Increased By ▲ 0.22 (0.37%)
UNITY 39.02 Increased By ▲ 2.53 (6.93%)
WTL 1.83 Increased By ▲ 0.08 (4.57%)
BR100 11,749 Increased By 48.7 (0.42%)
BR30 36,171 Increased By 760.4 (2.15%)
KSE100 109,970 Increased By 916.4 (0.84%)
KSE30 34,131 Increased By 281.6 (0.83%)

Toyota may have pioneered the just-in-time manufacturing strategy but when it comes to chips, its decision to stockpile what have become key components in cars goes back a decade to the Fukushima disaster.

After the catastrophe severed Toyota’s supply chains on March 11, 2011, the world’s biggest automaker realised the lead-time for semiconductors was way too long to cope with devastating shocks such as natural disasters.

That’s why Toyota came up with a business continuity plan (BCP) that required suppliers to stockpile anywhere from two to six months’ worth of chips for the Japanese carmaker, depending on the time it takes from order to delivery, four sources said.

And that’s why Toyota has so far been largely unscathed by a global shortage of semiconductors following a surge in demand for electrical goods under coronavirus lockdowns that has forced many rival automakers to suspend production, the sources said.

“Toyota was, as far as we can tell, the only automaker properly equipped to deal with chip shortages,” said a person familiar with Harman International, which specialises in car audio systems, displays and driver assistance technology.

Two of the sources who spoke to Reuters are Toyota engineers and the others are at companies involved in the chip business.

Toyota surprised rivals and investors last month when it said its output would not be disrupted significantly by chip shortages even as Volkswagen, General Motors, Ford, Honda and Stellantis, among others, have been forced to slow or suspend some production.

Toyota, meanwhile, has raised its vehicle output for the fiscal year ending this month and jacked up its full-year earnings forecast by 54%.

The source familiar with Harman said the company, part of South Korea’s Samsung Electronics, was experiencing shortages of central processing units (CPUs) and power management integrated circuits as early as November last year.

While Harman doesn’t make chips, because of its continuity deal with Toyota, it was obliged to prioritise the carmaker and ensure it had enough semiconductors to maintain supplies of its digital systems for four months, or more, the source said.

The chips in especially short supply now are microcontroller units (MCUs) which control an array of functions such as braking, acceleration, steering, ignition, combustion, tire pressure gauges and rain sensors, the four sources told Reuters.

However, Toyota changed the way it buys MCUs and other microchips after the 2011 earthquake, which caused a tsunami that killed more than 22,000 people and triggered a deadly meltdown at Fukushima’s nuclear power plant.

In the aftermath of the quake, Toyota estimated its procurement of more than 1,200 parts and materials might be affected and it drew up a list of 500 priority items that would need secure supply in the future, including semiconductors made by key Japanese chip supplier Renesas Electronics.

The repercussions of the disaster were so severe it took six months for Toyota to get production outside Japan back to normal levels, having done so at home two months earlier.

It was a big shock to Toyota’s just-in-time system because a smooth flow of components from suppliers to factories to assembly lines - as well as lean inventories - were central to its emergence as an industry leader for efficiency and quality.

At a time when supply chain risk is now front and centre in almost every industry, the move shows how Toyota was ready to throw out its own rule book when it came to semiconductors - and is reaping the rewards.

A Toyota spokesman said one of the goals of its lean inventories strategy was to become sensitive to inefficiencies and risks in supply chains, identify the most potentially damaging bottlenecks and figure out how to avoid them.

“The BCP for us was a classic lean solution,” he said.

Toyota pays for its stockpiling arrangement with chip suppliers by returning a portion of the cost cuts it demands from them each year during the life cycle of any car model under so-called annual cost-down programmes, the sources said.

Inventories of MCU chips - which often combine multiple technologies, CPUs, flash memory and other devices - are held for Toyota by parts suppliers such as Denso, which is partially owned by Toyota Group, chip makers like Renesas and Taiwan Semiconductor Manufacturing, and chip traders.

While there are different kinds of MCUs, those in short supply now are not cutting-edge chips but more mainstream ones with semiconductor nodes ranging from 28 to 40 nanometres, the sources said.

Toyota’s continuity plans for chips has also cushioned it from the impact of natural disasters exacerbated by climate change, such as fiercer typhoons and rain storms which often cause floods and landslides across Japan, including the southern Kyushu region manufacturing hub where Renesas also makes chips. One of the sources involved in semiconductor supply, said Toyota and its affiliates had become “extra risk averse and sensitive” to the impact of climate change. But natural disasters and are not the only threat on the horizon.—Reuters