BR100 Increased By (0.12%)
BR30 Increased By (0.28%)
KSE100 Increased By (0.26%)
KSE30 Increased By (0.26%)
AGHA 7.63 Increased By ▲ 0.04 (0.53%)
BECO 5.57 Increased By ▲ 0.06 (1.09%)
BML 59.74 Increased By ▲ 0.66 (1.12%)
BOP 34.40 Increased By ▲ 0.29 (0.85%)
CNERGY 13.11 Increased By ▲ 0.27 (2.1%)
CSIL 6.41 Increased By ▲ 0.31 (5.08%)
FCCL 58.06 Increased By ▲ 0.40 (0.69%)
FFL 16.23 Increased By ▲ 0.03 (0.19%)
FNEL 1.21 No Change ▼ 0.00 (0%)
KEL 7.43 Decreased By ▼ -0.05 (-0.67%)
KOSM 6.03 Increased By ▲ 0.09 (1.52%)
LOTCHEM 27.67 Decreased By ▼ -0.32 (-1.14%)
MLCF 102.75 Increased By ▲ 2.10 (2.09%)
NBP 205.06 Increased By ▲ 1.31 (0.64%)
NCPL 59.63 Decreased By ▼ -0.94 (-1.55%)
NPL 68.56 Decreased By ▼ -1.40 (-2%)
OGDC 318.92 Decreased By ▼ -1.37 (-0.43%)
PACE 11.05 Decreased By ▼ -0.05 (-0.45%)
PAEL 43.10 Decreased By ▼ -0.02 (-0.05%)
PIBTL 16.63 Increased By ▲ 0.07 (0.42%)
PPL 229.45 Increased By ▲ 0.61 (0.27%)
PRL 70.80 Decreased By ▼ -0.22 (-0.31%)
PTC 71.00 Decreased By ▼ -0.65 (-0.91%)
SSGC 27.41 Increased By ▲ 0.73 (2.74%)
TBL 10.31 Increased By ▲ 0.50 (5.1%)
TELE 8.53 Decreased By ▼ -0.08 (-0.93%)
TPL 23.06 Increased By ▲ 0.82 (3.69%)
TPLP 15.76 Increased By ▲ 0.65 (4.3%)
TREET 24.71 Increased By ▲ 0.58 (2.4%)
TRG 60.29 Increased By ▲ 0.45 (0.75%)
Top News

LCCI briefed on 4,320mw Dasu hydropower project

Published Updated

showiaaLAHORE: A five-member team of consultants of the 4,320mw Dasu hydropower project on Saturday gave a detailed briefing to Lahore Chamber of Commerce and Industry's office-bearers on the low-cost energy plant which will contribute 21.3 billion units of electricity to the national grid.

The benefits of the project have been estimated at about Rs 191.7 billion annually.

The consultants team, comprising IIJIMA Motohiko, Project Manager-Team Leader, Dasu Hydropower Project, Hiroyasu Kitayama, Chief Material Specialist, Nippon Koei Co, Ltd, Japan, Toshimitsu Tanaka, Nippon Koei Co, Ltd, Japan, Muhammad Munir, Managing Partner Development & Management Consultants (DMC) and Ziaul Hassan, Deputy Project Manager, discussed a number of technical issues with LCCI Senior Vice President Kashif Younis Meher.

After listening to the point of view of the visiting team, SVP Kashif Meher said the Lahore chamber was ready to extend every help so that work on the mega hydropower project of national importance could be started at the earliest.

He urged the consultants to have regular meetings at the LCCI as it had 18,000 members belonging to all sorts of businesses and they would be ready to facilitate the consultants.

When the visiting team discussed the issue regarding provision of Flyash (a residue of coal used in construction of dams), he said that the material could be made available in Pakistan and in this regard the LCCI would do the needful.

The Dasu hydropower project is situated at 7 km upstream of Dasu village on the Indus River, 74 km downstream of Diamer Basha Dam and 350 km from Islamabad. The project is located in district Kohistan of Khyber-Pakthunkhwa. Meher said the government's reliance on thermal generation had contracted hydel contribution in the total energy mix.

The policy of generating more electricity through thermal power plants resulted in expensive generation that widened the gap between the cost of production and sale.

Water and Power Development Authority (Wapda) had awarded the contract to a joint venture, Dasu Hydropower Consultants, for preparation of a detailed engineering design and construction supervision of the 4,320-megawatt Dasu hydropower project.

The joint venture comprises two foreign and three local consulting companies including Nippon Koei of Japan, Dolsar Engineering of Turkey, Development and Management Consultants, National Development Consultants and Pakistan Engineering Services.

Copyright APP (Associated Press of Pakistan), 2011