AIRLINK 61.75 Increased By ▲ 1.32 (2.18%)
BOP 5.36 Increased By ▲ 0.01 (0.19%)
CNERGY 4.57 Decreased By ▼ -0.03 (-0.65%)
DFML 15.83 Increased By ▲ 0.99 (6.67%)
DGKC 66.23 Increased By ▲ 1.43 (2.21%)
FCCL 17.25 Increased By ▲ 0.39 (2.31%)
FFBL 28.02 Increased By ▲ 3.27 (13.21%)
FFL 9.26 Increased By ▲ 0.20 (2.21%)
GGL 10.30 Increased By ▲ 0.34 (3.41%)
HBL 105.30 Increased By ▲ 1.09 (1.05%)
HUBC 122.63 Increased By ▲ 5.11 (4.35%)
HUMNL 6.55 Increased By ▲ 0.01 (0.15%)
KEL 4.54 Decreased By ▼ -0.01 (-0.22%)
KOSM 4.48 Decreased By ▼ -0.09 (-1.97%)
MLCF 36.22 Increased By ▲ 0.81 (2.29%)
OGDC 123.28 Increased By ▲ 0.89 (0.73%)
PAEL 22.75 Increased By ▲ 0.84 (3.83%)
PIAA 29.34 Increased By ▲ 2.05 (7.51%)
PIBTL 5.86 Decreased By ▼ -0.08 (-1.35%)
PPL 106.21 Decreased By ▼ -1.16 (-1.08%)
PRL 27.28 Increased By ▲ 0.77 (2.9%)
PTC 18.39 Increased By ▲ 2.29 (14.22%)
SEARL 53.20 Decreased By ▼ -0.43 (-0.8%)
SNGP 63.96 Increased By ▲ 2.76 (4.51%)
SSGC 10.85 Increased By ▲ 0.10 (0.93%)
TELE 9.42 Increased By ▲ 0.93 (10.95%)
TPLP 11.34 Increased By ▲ 0.76 (7.18%)
TRG 72.72 Increased By ▲ 2.81 (4.02%)
UNITY 23.85 Increased By ▲ 0.34 (1.45%)
WTL 1.30 Increased By ▲ 0.02 (1.56%)
BR100 6,955 Increased By 76.8 (1.12%)
BR30 22,862 Increased By 293.4 (1.3%)
KSE100 67,173 Increased By 625.4 (0.94%)
KSE30 22,116 Increased By 201.5 (0.92%)
Business & Finance

China ready to include Diamer-Bhasha Project in CPEC

ISLAMABAD: The National Assembly Standing Committee on Planning, Development and Reform was informed on Monday tha
Published June 21, 2017

ISLAMABAD: The National Assembly Standing Committee on Planning, Development and Reform was informed on Monday that China has offered Pakistan to include the Diamer-Bhasha dam project in China-Pakistan Economic Corridor (CPEC).

Muzammil Hussain, Water and Power Development Authority (Wapda) Chairman, said that governments of Pakistan and China were seriously mulling over including the Diamer-Bhasha project in CPEC as no mega hydel project was included in economic corridor, according to APP.

The completion of project went in abeyance earlier in 2006 when the Asian Development Bank committed to funding the project refused to provide funds after 10 years, saying the project was situated in a dispute territory.

Hussain said PC-1 of the project holding 4,500MW installed capacity had already been completed and 85% land acquisition had also been made by the government.

The Wapda chairman told the committee that the project needed $14.49 billion for the completion that hindered due to issues in fund allocation.

He informed that other hydel power projects including Neelum-Jhelum and Tarbela extension would be completed by May 2018, which would provide an additional 2,500MW of electricity.

Work on the 800MW Mohmand Dam and power project would be initiated by March 2018 whereas Munda Dam project would also be started by the first quarter of next year. However, there was no funding problem for either of the two projects, he added.

The committee was apprised that work on the Dasu project would start by next month and it would be completed by 2022. This project will help produce 2,500MW.

The committee told the Ministry of Water and Power to submit its fund release policy in the next meeting.