BR100 Increased By (0.01%)
BR30 Increased By (0.53%)
KSE100 Increased By (0.28%)
KSE30 Increased By (0.29%)
AGHA 6.38 Increased By ▲ 0.06 (0.95%)
BECO 4.35 Increased By ▲ 0.08 (1.87%)
BML 62.55 Increased By ▲ 0.10 (0.16%)
BOP 31.39 Increased By ▲ 0.16 (0.51%)
CNERGY 11.73 Increased By ▲ 0.14 (1.21%)
CSIL 5.91 Increased By ▲ 0.19 (3.32%)
FCCL 61.71 Increased By ▲ 0.17 (0.28%)
FFL 14.79 Decreased By ▼ -0.23 (-1.53%)
FNEL 1.24 Increased By ▲ 0.01 (0.81%)
KEL 6.32 Increased By ▲ 0.06 (0.96%)
KOSM 5.90 Increased By ▲ 0.34 (6.12%)
LOTCHEM 24.69 Increased By ▲ 0.01 (0.04%)
MLCF 103.93 Decreased By ▼ -0.15 (-0.14%)
NBP 173.32 Decreased By ▼ -1.96 (-1.12%)
NCPL 51.83 Decreased By ▼ -0.94 (-1.78%)
NPL 54.03 Decreased By ▼ -0.09 (-0.17%)
OGDC 315.87 Increased By ▲ 2.48 (0.79%)
PACE 9.26 Increased By ▲ 0.06 (0.65%)
PAEL 35.58 Decreased By ▼ -0.22 (-0.61%)
PIBTL 13.66 Increased By ▲ 0.19 (1.41%)
PPL 226.07 Increased By ▲ 4.26 (1.92%)
PRL 80.28 Increased By ▲ 1.20 (1.52%)
PTC 46.64 Decreased By ▼ -0.21 (-0.45%)
SSGC 23.82 Decreased By ▼ -0.05 (-0.21%)
TBL 9.24 Decreased By ▼ -0.07 (-0.75%)
TELE 7.55 Increased By ▲ 0.16 (2.17%)
TPL 24.54 Decreased By ▼ -0.57 (-2.27%)
TPLP 12.99 Increased By ▲ 0.48 (3.84%)
TREET 25.98 Decreased By ▼ -0.27 (-1.03%)
TRG 53.33 Decreased By ▼ -0.11 (-0.21%)

JAKARTA: Operation of Train 3 at BP's Tangguh liquefied natural gas plant in Indonesia is expected to be delayed by a year, Fatar Yani Abdurrahman, deputy chief of upstream oil and gas regulator SKK Migas, told reporters.

It is expected to begin in the third quarter of 2021 versus at initial target of the third quarter of 2020, he said.

A number of natural disasters across Indonesia have delayed shipments of construction material needed in Tangguh, he said, adding that financial difficulty faced by one contractor had also hampered progress.

BP Indonesia head Moektianto Soeryowibowo confirmed to Reuters there had been an issue with a contractor and said the company was in discussions with its partners, the contractor consortium, and the government on how to best mitigate the impact on costs and schedule.

"Work on the onshore engineering, procurement and construction being carried out by the Chiyoda-Saipem-Tripatra-Suluh Ardhi Engineering (CSTS) consortium is being impacted by several factors and requires additional work," Soeryowibowo said by text message.

He noted that the Tangguh Train 3 project, which currently has 7,000 workers on site, "will add a production capacity of 3.8 million tons of LNG per year (mtpa), bringing Tangguh's plant total capacity to 11.4 mtpa."

Copyright Reuters, 2019