BR100 Increased By (0.03%)
BR30 Increased By (0.03%)
KSE100 Increased By (0.04%)
KSE30 Increased By (0.04%)
AGHA 6.52 Increased By ▲ 0.20 (3.16%)
BECO 4.40 Increased By ▲ 0.13 (3.04%)
BML 62.40 Decreased By ▼ -0.05 (-0.08%)
BOP 31.40 Increased By ▲ 0.17 (0.54%)
CNERGY 11.75 Increased By ▲ 0.16 (1.38%)
CSIL 6.01 Increased By ▲ 0.29 (5.07%)
FCCL 60.67 Decreased By ▼ -0.87 (-1.41%)
FFL 14.90 Decreased By ▼ -0.12 (-0.8%)
FNEL 1.25 Increased By ▲ 0.02 (1.63%)
KEL 6.29 Increased By ▲ 0.03 (0.48%)
KOSM 5.76 Increased By ▲ 0.20 (3.6%)
LOTCHEM 24.75 Increased By ▲ 0.07 (0.28%)
MLCF 102.81 Decreased By ▼ -1.27 (-1.22%)
NBP 174.50 Decreased By ▼ -0.78 (-0.45%)
NCPL 52.99 Increased By ▲ 0.22 (0.42%)
NPL 54.67 Increased By ▲ 0.55 (1.02%)
OGDC 313.94 Increased By ▲ 0.55 (0.18%)
PACE 9.28 Increased By ▲ 0.08 (0.87%)
PAEL 35.50 Decreased By ▼ -0.30 (-0.84%)
PIBTL 13.65 Increased By ▲ 0.18 (1.34%)
PPL 222.00 Increased By ▲ 0.19 (0.09%)
PRL 80.34 Increased By ▲ 1.26 (1.59%)
PTC 47.01 Increased By ▲ 0.16 (0.34%)
SSGC 23.96 Increased By ▲ 0.09 (0.38%)
TBL 9.27 Decreased By ▼ -0.04 (-0.43%)
TELE 7.47 Increased By ▲ 0.08 (1.08%)
TPL 24.70 Decreased By ▼ -0.41 (-1.63%)
TPLP 12.97 Increased By ▲ 0.46 (3.68%)
TREET 26.10 Decreased By ▼ -0.15 (-0.57%)
TRG 54.34 Increased By ▲ 0.90 (1.68%)
World

India proposes transmission charge relief for delayed renewable projects

  • Several clean energy projects have been stalled in India because of a lack of transmission infrastructure
Published Updated
Photo: Reuters
Photo: Reuters
By

NEW DELHI: India’s power regulator has proposed giving transmission charge waivers to clean energy projects that have been delayed by the unavailability of transmission lines, draft regulations showed.

Several clean energy projects have been stalled in India because of a lack of transmission infrastructure.

The move would mark a policy roll-back. India had begun phasing out interstate transmission charge waivers for new solar, wind and hybrid projects from July 2025.

The draft proposal from the Central Electricity Regulatory Commission would benefit solar, wind and hybrid renewable energy projects that missed their commissioning timelines.

The relief would be available for projects that signed at least seven-year-long power sale contracts by December 31, 2026.

The regulator also proposed extending these benefits to battery storage systems that are built as part of renewable energy projects.

In such cases, power supplied from the batteries would get the same transmission-charge waiver as the renewable project itself.