BR100 Increased By (0.14%)
BR30 Decreased By (-0.19%)
KSE100 Increased By (0.12%)
KSE30 Increased By (0.09%)
AGHA 7.79 Increased By ▲ 0.04 (0.52%)
BECO 5.23 Increased By ▲ 0.04 (0.77%)
BML 57.26 Decreased By ▼ -1.40 (-2.39%)
BOP 34.10 Increased By ▲ 0.41 (1.22%)
CNERGY 9.92 Decreased By ▼ -0.69 (-6.5%)
CSIL 5.35 Increased By ▲ 0.05 (0.94%)
FCCL 54.61 Increased By ▲ 0.87 (1.62%)
FFL 16.70 Increased By ▲ 0.24 (1.46%)
FNEL 1.24 Increased By ▲ 0.02 (1.64%)
KEL 7.42 Increased By ▲ 0.14 (1.92%)
KOSM 5.75 Increased By ▲ 0.11 (1.95%)
LOTCHEM 29.35 Decreased By ▼ -0.30 (-1.01%)
MLCF 94.35 Decreased By ▼ -2.01 (-2.09%)
NBP 202.70 Decreased By ▼ -0.83 (-0.41%)
NCPL 57.00 Increased By ▲ 0.15 (0.26%)
NPL 67.78 Increased By ▲ 0.47 (0.7%)
OGDC 316.40 Decreased By ▼ -1.82 (-0.57%)
PACE 10.64 Increased By ▲ 0.01 (0.09%)
PAEL 43.15 Increased By ▲ 1.38 (3.3%)
PIBTL 16.72 Decreased By ▼ -0.09 (-0.54%)
PPL 220.50 Increased By ▲ 0.33 (0.15%)
PRL 49.05 No Change ▼ 0.00 (0%)
PTC 70.98 Increased By ▲ 0.97 (1.39%)
SSGC 28.17 Decreased By ▼ -0.97 (-3.33%)
TBL 9.90 Increased By ▲ 0.13 (1.33%)
TELE 8.80 Decreased By ▼ -0.02 (-0.23%)
TPL 18.14 Increased By ▲ 0.97 (5.65%)
TPLP 13.40 Increased By ▲ 0.89 (7.11%)
TREET 22.75 Increased By ▲ 0.16 (0.71%)
TRG 60.30 Increased By ▲ 0.08 (0.13%)

ISLAMABAD: This is apropos a news report “$5bn Chashma-5 N-Plant to produce power at Rs 20 per unit: Country has swallowed a bitter bill?” published by Business Recorder on 12 July 2023. Pakistan Atomic Energy Commission (PAEC) appreciates the due diligence put in by the author. However, PAEC is of the view that some misconceptions in the story demand clarification in order to set the record straight.

Firstly, the cost of upcoming Chashma Nuclear Power Plant Unit-5 (C-5) in the report is claimed to be $5 billion. Whereas, the details of the loan for C-5 are as follows: The total loan for C-5 is 21318 million RMB ($2.94 bn), PAEC will not be liable to make any foreign exchange (FE) payments for the first eight years – the favour was earned by PAEC keeping in view the financial constraints of the country.

Secondly, the C-5 plant will be sited at CNPGS near Kundian in District Mianwali, where four nuclear power plants (NPPs) C-1 to C-4 are already operational and are supplying 1330 MW electricity to the national grid which implies low/ negligible transmission cost as compared to other base load projects.

$5bn Chashma-5 N-plant to produce power at Rs20 per unit: Country has swallowed a bitter pill?

Thirdly, the levelized per unit cost of electricity produced at C-5 NPP is Rs.13.9 instead of Rs.20 per unit as claimed by the author.

Fourthly, the project of C-5 is not ‘a bitter pill’; it is rather a tonic that will boost our industrial sector; the Project’s local equipment of worth $120 million will be bought from Pakistani suppliers, saving precious foreign exchange as well as bringing in an era of highly specialised and high-tech manufacturing. Moreover, local sand, cement, crush and steel industries will also be extensively involved in the project.

Fifthly, through C-5 project’s execution the country will gain industrial strength by exporting the specialized equipments for any future foreign projects of China.

Sixthly, C-5 project gives flexibility to our means of power generation by providing essentially required diversity to the existing sources of energy. Lastly, C-5 is a clean energy project which not only saves heavy capital used for fossil fuel imports, but also contributes to the global efforts to decarbonize the energy system using nuclear power, and explore nuclear’s potential contribution towards net-zero targets.

Copyright Business Recorder, 2023

Comments

Comments are closed for this article.

amir Jul 14, 2023 07:07pm
A truely bebeficial project likey to bring a sigh of relief to the consumers. Financial model is extraodinary. repayment will start after one year of earnig and in RMBs not in dollars.no precedence in the history. welldone PAEC
0
usman Jul 14, 2023 09:48pm
This project will bring jobs and prosperity in the country especially for the people of Mianwali
0
Awais Ahmad Qureshi Jul 14, 2023 11:07pm
Alas sanity prevails amongst echelons of government officials....if they had taken such decisions in 2013 at start of CPEC we might not be facing a colossal circular debt issue today...bad decisions took by PML N for the sake of political gains at that time and now whole nation is agonising...