BR100 Decreased By (-0.81%)
BR30 Decreased By (-1.11%)
KSE100 Decreased By (-0.81%)
KSE30 Decreased By (-0.81%)
AGHA 7.59 Decreased By ▼ -0.10 (-1.3%)
BECO 5.51 Increased By ▲ 0.27 (5.15%)
BML 59.08 Decreased By ▼ -1.14 (-1.89%)
BOP 34.11 Decreased By ▼ -1.17 (-3.32%)
CNERGY 12.84 Decreased By ▼ -0.29 (-2.21%)
CSIL 6.10 Decreased By ▼ -0.01 (-0.16%)
FCCL 57.66 Decreased By ▼ -0.31 (-0.53%)
FFL 16.20 Decreased By ▼ -0.22 (-1.34%)
FNEL 1.21 Increased By ▲ 0.01 (0.83%)
KEL 7.48 No Change ▼ 0.00 (0%)
KOSM 5.94 Decreased By ▼ -0.10 (-1.66%)
LOTCHEM 27.99 Increased By ▲ 0.24 (0.86%)
MLCF 100.65 Decreased By ▼ -2.33 (-2.26%)
NBP 203.75 Decreased By ▼ -2.29 (-1.11%)
NCPL 60.57 Decreased By ▼ -1.67 (-2.68%)
NPL 69.96 Decreased By ▼ -1.33 (-1.87%)
OGDC 320.29 Decreased By ▼ -3.49 (-1.08%)
PACE 11.10 Decreased By ▼ -0.41 (-3.56%)
PAEL 43.12 Decreased By ▼ -0.78 (-1.78%)
PIBTL 16.56 Decreased By ▼ -0.12 (-0.72%)
PPL 228.84 Decreased By ▼ -0.63 (-0.27%)
PRL 71.02 Increased By ▲ 0.91 (1.3%)
PTC 71.65 Decreased By ▼ -0.50 (-0.69%)
SSGC 26.68 Decreased By ▼ -0.43 (-1.59%)
TBL 9.81 Decreased By ▼ -0.05 (-0.51%)
TELE 8.61 Decreased By ▼ -0.11 (-1.26%)
TPL 22.24 Decreased By ▼ -0.38 (-1.68%)
TPLP 15.11 Decreased By ▼ -0.57 (-3.64%)
TREET 24.13 Decreased By ▼ -0.08 (-0.33%)
TRG 59.84 Decreased By ▼ -1.29 (-2.11%)

LAHORE: In a major development towards implementation of Dasu Hydropower Project, Stage 1 of the concrete-Starter Dam has been completed upstream of Main Dam site.

As per the design, the Starter Dam for Dasu Hydropower Project is to be completed in two stages; Stage 1 up to elevation of 785 meters while Stage 2 up to elevation of 798 meters above mean sea level. The Stage 1 of the concrete Starter Dam was completed in June this year before the high flow season – a major landmark which the project team successfully achieved.

As the high flow season has started, River Indus is flowing through the two Diversion Tunnels completed earlier this year, while some of the river water is overtopping the concrete Starter Dam as designed.

After the high flow season in October this year, the construction of the Starter Dam’s Stage 2 will be carried out. The Stage 2 is scheduled for completion during the coming low flow season.