BR100 Increased By (0.9%)
BR30 Increased By (1.11%)
KSE100 Increased By (0.9%)
KSE30 Increased By (1%)
AGHA 6.44 Increased By ▲ 0.06 (0.94%)
BECO 4.36 Increased By ▲ 0.01 (0.23%)
BML 62.56 Increased By ▲ 0.01 (0.02%)
BOP 31.48 Increased By ▲ 0.09 (0.29%)
CNERGY 11.82 Increased By ▲ 0.09 (0.77%)
CSIL 5.76 Decreased By ▼ -0.15 (-2.54%)
FCCL 61.63 Decreased By ▼ -0.08 (-0.13%)
FFL 14.85 Increased By ▲ 0.06 (0.41%)
FNEL 1.29 Increased By ▲ 0.05 (4.03%)
KEL 6.35 Increased By ▲ 0.03 (0.47%)
KOSM 5.83 Decreased By ▼ -0.07 (-1.19%)
LOTCHEM 24.82 Increased By ▲ 0.13 (0.53%)
MLCF 106.20 Increased By ▲ 2.27 (2.18%)
NBP 174.43 Increased By ▲ 1.11 (0.64%)
NCPL 52.06 Increased By ▲ 0.23 (0.44%)
NPL 54.60 Increased By ▲ 0.57 (1.05%)
OGDC 319.54 Increased By ▲ 3.67 (1.16%)
PACE 9.30 Increased By ▲ 0.04 (0.43%)
PAEL 35.74 Increased By ▲ 0.16 (0.45%)
PIBTL 14.23 Increased By ▲ 0.57 (4.17%)
PPL 229.80 Increased By ▲ 3.73 (1.65%)
PRL 81.59 Increased By ▲ 1.31 (1.63%)
PTC 46.96 Increased By ▲ 0.32 (0.69%)
SSGC 24.00 Increased By ▲ 0.18 (0.76%)
TBL 9.24 No Change ▼ 0.00 (0%)
TELE 7.59 Increased By ▲ 0.04 (0.53%)
TPL 24.94 Increased By ▲ 0.40 (1.63%)
TPLP 12.95 Decreased By ▼ -0.04 (-0.31%)
TREET 26.03 Increased By ▲ 0.05 (0.19%)
TRG 53.57 Increased By ▲ 0.24 (0.45%)

LAHORE: In a major development towards implementation of Dasu Hydropower Project, Stage 1 of the concrete-Starter Dam has been completed upstream of Main Dam site.

As per the design, the Starter Dam for Dasu Hydropower Project is to be completed in two stages; Stage 1 up to elevation of 785 meters while Stage 2 up to elevation of 798 meters above mean sea level. The Stage 1 of the concrete Starter Dam was completed in June this year before the high flow season – a major landmark which the project team successfully achieved.

As the high flow season has started, River Indus is flowing through the two Diversion Tunnels completed earlier this year, while some of the river water is overtopping the concrete Starter Dam as designed.

After the high flow season in October this year, the construction of the Starter Dam’s Stage 2 will be carried out. The Stage 2 is scheduled for completion during the coming low flow season.