Thar coal to produce first electron in December as first layer of coal unearths    

12 Jun, 2018

The mining firm’s machinery took out the first layer from an estimated 2.04 billion tons of coal resources in Thar Coal Block II after successfully dewatering the second acquirer, five months ahead of schedule.

The full-fledged coal supply will start from third quarter 2018 and the first electron will be generated from the Engro Powergen Thar Limited (EPTL) power plant in December this year, according to a statement issued by SECMC.

The successful extraction of the first coal seam not only proves that Thar’s indigenous coal is exploitable but can produce thousands of megawatts of cheap electricity for many decades, announced Chief Executive Officer of SECMC Shamsuddin Shaikh after witnessing the coal unearthing at the bottom of the mine pit in Thar Coal Block II.

A Joint Venture between Sindh Government and six private sponsors including Engro Energy, Thal Ltd, Habib Bank Ltd, Hubco, and two Chinese companies CMEC and SPIC, SECMC is the largest Public Private Partnership in Pakistan to explore and develop Pakistan’s first open-pit coal mine with an annual output of 3.8 million tons.

The entire coal production will be supplied to EPTL which is putting up a 2x330 MW mine-mouth power plant which is targeting to start power generation before the end of this year. Both these projects are part of the China Pakistan Economic Corridor (CPEC) and are being constructed in collaboration with Chinese Contractors.

Congratulating the nation, especially the people of Thar, Shaikh said that it’s a matter of great pride for the nation that country’s indigenous energy resource will play a key role in circumventing the current energy crisis.

“This is the moment for which all Pakistanis had been waiting for the past 25 years, ever since coal was first discovered in Thar,” said Shaikh.

He thanked all the sponsors of this mega project, lenders, Federal Government and especially Sindh Government for providing whole-hearted support to make the dream of Thar a reality.

Commenting on the performance of SECMC, Mr. Shaikh added "we have completed 16 million safe man-hours while removing 90 million cubic meters of overburden (earth), and we did it 5 months ahead schedule, and targeting a savings of USD 110 million versus the budgeted cost, all of which is unprecedented for a mega project like this."

Sharing the future plans, Shaikh said that Company plans to rapidly expand the mine in Block-II to reach its optimum capacity to produce 5000 MWs by 2024 which will drastically reduce the coal price making Thar Block-II not only the cheapest block in Thar, it will be the cheapest base load energy resource in the Country with a power tariff of approximately 5 US cents per kWH.

He requested both the federal and provisional governments to hold the development of all other coal blocks in Thar till SECMC’s Block II reaches its optimum capacity which will allow Thar coal to provide the cheapest electricity to consumers. Commenting on the CSR work being done by the Company in Thar, Mr Shaikh said that "we are committed to making Islamkot an accelerated Taluka for attaining the United Nation’s Sustainable Development Goals (SDGs) by 2024".

Meanwhile Chief Operating Officer of SECMC Syed Abul Fazal Rizvi, said that the coal in Thar is called lignite which is ideally suited for producing electricity. With a cumulative thickness around 26 meters, there are enough coal reserves in Block-II to produce 5000 MW for the next 50 years,” Rizvi said.

He reiterated the commitment to continue serving the energy sector of Pakistan and especially the people of Thar who shall be the real beneficiary of this black gold.

Copyright APP (Associated Press of Pakistan), 2018