Opinion

Neelum-Jhelum before commissioning: design was the first warning (Part-I)

  • A shift to a larger, riskier design for Neelum-Jhelum multiplied geological and financial burdens
Published Updated
7 min
Summary new

Neelum-Jhelum did not become a problem after commissioning. It entered service carrying the consequences of choices made much earlier: a bigger design, deeper tunnels, weaker risk discipline, inflated costs and a strategic narrative that made hard questioning politically inconvenient.

The original concept was sound. Pakistan needed indigenous hydropower. The Neelum River offered real generation potential. The Kishanganga dispute with India gave the project strategic urgency. A timely, technically conservative scheme could have supplied low-cost electricity, reduced fuel-import dependence and strengthened Pakistan’s water-use position.

But the project did not remain technically conservative. The decisive planning shift was from a smaller, shorter and less hazardous layout to the eventual 969 MW scheme. The earlier option appears to have involved a lower head and simpler tunnel alignment. The revised design pursued a much higher head through a longer underground waterway system, raising the installed capacity but multiplying geological and construction risk.

That trade-off was the heart of the matter. Pakistan bought roughly 400 MW of additional headline capacity by accepting a vastly more complex tunnel system. The public heard the capacity number. It did not hear, with equal clarity, the price of that number: longer tunnels, deeper excavation, greater hydraulic pressure, weaker rock exposure, seismic sensitivity, construction uncertainty and a much heavier financial burden.

A megawatt in a planning document is cheap. A megawatt inside a mountain is not.

The larger design had obvious appeal. It was grander, more marketable and more useful for official speeches. But engineering is not public relations. Capacity only matters if the plant can be built safely, financed rationally and operated reliably for decades. On that test, Neelum-Jhelum’s planning stage deserved far more scepticism than it received.

The project soon acquired three dangerous features. First, it was labelled strategic, which made criticism look unpatriotic. Second, it was framed as a race with India, which encouraged haste without discipline. Third, its cost kept rising, which made reversal politically harder with each passing year. Once such a project gathers momentum, bureaucracy protects the momentum more fiercely than the public interest.

The race-with-India argument was not imaginary, but it was misused. India’s Kishanganga project was a genuine concern. Pakistan had reason to move quickly. But urgency should have meant sharper decision-making, not weaker scrutiny. Instead, the country invoked speed while moving slowly, and invoked strategy while tolerating cost escalation and design uncertainty.

The project cost tells its own story. What began as a far more modest undertaking crossed the Rs500 billion mark by the time of final approval. That cannot be explained away as inflation. It reflected design ambition, financing delays, geological surprises, contract changes and weak project control. In any serious system, a cost explosion of that scale would have triggered a pause, an independent review and a public explanation.

The dollar cost is even more damning than the rupee headline suggests. ECNEC ultimately approved the project at Rs506.8 billion in 2018. This was not merely a WAPDA balance-sheet number: the project equity was partly built from electricity consumers through the Neelum-Jhelum surcharge collected in their power bills. Dividing the final rupee cost by the 2018 exchange rate also understates the burden because much of the expenditure occurred when the rupee was stronger. Converting estimated annual construction spending at each year’s average official exchange rate places the nominal dollar cost at roughly USD5.1 billion, or about USD5.3 million per MW. The Planning Commission’s own third-party validation terms put the unit construction cost at USD4.23 million per MW and compared it with Dasu at USD2.25 million, Bunji at USD1.87 million, Diamer-Basha at USD2.48 million and Lower Palas at USD1.66 million per MW. One newspaper reported Neelum-Jhelum’s Rs523 million per MW cost as the highest by local and global standards. On any fair benchmark, this became one of the most expensive tunnel-heavy run-of-river hydropower projects of comparable scale; if there is a more expensive example of its nature, the public has never been shown it.

A broader international comparison removes the last refuge of excuses. The relevant benchmark is not an ordinary dam or a thermal plant, but other diversion, tunnel-heavy or run-of-river hydropower schemes. The picture is brutal:

Project

Comparable nature

MW

Approx. cost

US$m/MW

Neelum-Jhelum (Pakistan)

Tunnel-heavy run-of-river/diversion

969

US$5.1bn

5.3

Bujagali (Uganda)

Hydropower/pondage benchmark

250

US$0.80bn

3.2

Xayaburi (Laos)

Run-of-river Mekong scheme

1,285

US$3.8bn

3.0

Kishanganga

High-head run-of-river/diversion

330

US$0.86bn

2.6

Karot (Pakistan/Jhelum)

Regional run-of-river benchmark

720

US$1.70bn

2.4

Nam Theun 2 (Laos)

Trans-basin hydropower

1,070

US$1.45bn

1.4

Tala (Bhutan)

High-head run-of-river, long tunnel

1,020

US$0.90bn

0.9

Jinping-II (China)

Mega diversion, 4 x 16.6km tunnels

4,800

US$3.73bn

0.8

Even allowing for differences in terrain, project year, scope, transmission treatment and exchange rates, Neelum-Jhelum remains an outlier. It is more expensive per MW than Kishanganga, Karot, Xayaburi, Nam Theun 2, Tala and even China’s giant Jinping-II diversion project. That is the true comparison: Pakistan paid a premium price for a project that still failed to deliver premium reliability.

The missing question was brutally simple: was the additional capacity worth the additional risk? If a smaller scheme could have delivered substantial power earlier and at lower risk, the larger option needed a hard economic and engineering defence. That defence should have been revisited after the 2005 earthquake, when the region’s geological and seismic risks became impossible to ignore. Instead, the larger design remained the path of least resistance inside the project machinery.

By the time construction moved into full execution, the central decision had already been made. Implementation teams then inherited the consequences: difficult tunnelling, rock stress, pressure issues, delays and rising costs. Later controversies over tunnelling methodology were not isolated management glitches. They were symptoms of a design whose risk profile had been under-absorbed at the planning stage.

The tunnel boring machine story captures the same failure in metal form. The TBMs were brought in to fast-track excavation; instead, their installation reportedly took seven months and their removal and dismantling was expected to take another seven. Muzammil Hussain later told a cabinet committee that the machines were a poor decision, linked their use with hundreds of rock-burst incidents, human casualties, damage to one TBM and the awkward fact that one machine remained stuck in the tunnel. He also noted that disposal was itself a problem because the contract carried a salvage value of USD4.065 million, while the machines were custom-made for Neelum-Jhelum and not usable elsewhere in Pakistan. The Planning Commission’s third-party validation terms separately recorded the TBM cost at Rs19.5 billion and called for scrutiny of alleged procurement-rule violations. The instrument bought to save time became another exhibit in how haste, weak geology, poor contracting and thin accountability can turn engineering equipment into stranded capital.

This is why later remarks by WAPDA Chairman Muzammil Hussain were so significant. He reportedly described Neelum-Jhelum as poorly designed and ill-conceived from the beginning, citing weak surveys, vague estimates, rock bursting, water seepage and mid-course changes. That was not a minor criticism. It was an institutional admission that the project had been structurally flawed before it became operational.

Yet Pakistan treated the warning as another item in the archive. No national reckoning followed. No full public account was placed before consumers, taxpayers or Parliament explaining why the larger design was chosen, who evaluated the geological risk, what alternatives were rejected and how the cost-benefit case changed over time.

Before commissioning, Neelum-Jhelum already displayed the classic symptoms of Pakistani mega-project failure: inflated ambition, weak scrutiny, strategic sloganeering, delayed execution and blurred accountability. The project was too important to question, too expensive to stop and too politically useful to examine honestly.

Commissioning later provided a photograph, not a verdict. The deeper verdict had already been written into the design. Pakistan chose the grander tunnel-heavy scheme and failed to build the governance discipline needed to match it.

Neelum-Jhelum’s first tragedy was therefore not the tunnel collapse. The first tragedy was that the design risk was visible before generation began, yet the state marched ahead as if ambition itself were an engineering solution.

Author Image

Shahid Sattar

PUBLIC SECTOR EXPERIENCE: He has served as Member Energy of the Planning Commission of Pakistan & has also been an advisor at: Ministry of Finance Ministry of Petroleum Ministry of Water & Power

PRIVATE SECTOR EXPERIENCE: He has held senior management positions with various energy sector entities and has worked with the World Bank, USAID and DFID since 1988. Mr. Shahid Sattar joined All Pakistan Textile Mills Association in 2017 and holds the office of Executive Director and Secretary General of APTMA.

He has many international publications and has been regularly writing articles in Pakistani newspapers on the industry and economic issues which can be viewed in Articles & Blogs Section of this website.

Read Also