Rs36,218mn released for various power projects so far

23 Dec, 2015

ISLAMABAD: The Planning Commission has released Rs 36,218.026 million against total allocation of Rs 112,318.285 million in annual Public Sector Development Programme (PSDP) 2015-16 for various power projects so far.

According to the data of Planning Commission, as many as Rs.14,160 million was released for 1200 MW LNG Based Power Plant Baloki and Rs.21970 million for 1200 MW LNG Based Power Plant Haveli Bahadur Shah.

Similarly, an amount of Rs 45.400 million was released for 33 KV Transmission Line from 132 KV Grid Stations Thana Bula Khan District Jamshoro HESCO to Dureji, (Sub Station at Dureji) and Rs 42.625 million for Construction of 132 KV Sui Grid Station & Kashmore - Sui Transmission Line Meanwhile, a sum of Rs 11,719.110 million has been released against total allocation of Rs 30,120 million in annual PSDP 2015-16 for various water powers.

Copyright APP (Associated Press of Pakistan), 2015