NEPRA has accorded final approval of the Tripartite Power Purchase Agreement made between K-Electric, NTDC and CPPA-G for supply of 150 MW from National Grid to K-Electric through 03 WPPs i.e. namely 50 MW Tenaga, 50 MW Zephyr and 50 MW Hydro China Dawood.
Work on the 220 kV Dhabeji Grid and transmission lines has started and finalization of contractual arrangements for the off-take of additional 1,400 MW from National Grid (including 450 MW from existing interconnections) is in advanced stages.
As per details, KE has requested NEPRA to increase the price of electricity for four months and reduce it for three months for monthly Fuel Charges Adjustments.