ISLAMABAD: The Planning Commission of Pakistan has so far released Rs. 105.7 billion under its PSDP against the total allocations of Rs. 233 billion for the fiscal year 2012-13, according to the latest data of the commission released here.
Some Rs. 57.4 billion has been released for 345 infrastructure development projects and Rs 45.1 billion for 688 social sector projects. Similarly, Rs. 1.2 billion has been released for 71 other projects and Rs. 2 billion for the Earthquake Reconstruction and Rehabilitation Authority. The releases have been made against Rs 233 allocations.
It is pertinent to mention here that the total size of the PSDP for the year 2012-13 is Rs. 360 billion, including Rs. 100 billion foreign aid, which is managed by Economic Affairs Division and Rs. 27 billion special programmes, release of which are made by Cabinet Division or Finance Division.
According to break up details, the total cost of 345 infrastructure projects has been estimated at Rs. 2320.3 billion, out of which, Rs.211.1 billion have been earmarked in the 2012-13 budget that include Rs. 85.6 billion as foreign aid.
Likewise, the total cost of social sector projects is Rs. 549.8 billion, of which, Rs. 135.9 billion has been allocated in the current PSDP with foreign aid of Rs. 8.4 percent.
The cost of other projects has been estimated at Rs. 41.3 billion out of which Rs. 3 billion has been earmarked in the PSDP 2012-13 while Rs. 10 billion has been earmarked for ERRA in the current development programme.
The Planning Commission of Pakistan has been following a proper mechanism for the release of funds and accordingly funds are released as per given mechanism.
The commission releases 20pc of funds in first quarter (July-September), 20pc in second quarter (October-December), 25pc third quarter (January-March) and 35pc in fourth quarter (April-June).