BR100 Increased By (1.77%)
BR30 Increased By (1.96%)
KSE100 Increased By (1.59%)
KSE30 Increased By (1.65%)
BECO 5.62 Increased By ▲ 0.04 (0.72%)
BML 59.51 Decreased By ▼ -1.71 (-2.79%)
BOP 34.61 Increased By ▲ 0.93 (2.76%)
CNERGY 8.08 No Change ▼ 0.00 (0%)
DCL 12.05 Increased By ▲ 0.41 (3.52%)
FCCL 54.40 Increased By ▲ 2.26 (4.33%)
FCSC 5.52 Decreased By ▼ -0.11 (-1.95%)
FFL 18.05 Increased By ▲ 0.04 (0.22%)
FNEL 1.33 Decreased By ▼ -0.02 (-1.48%)
HUMNL 11.07 Increased By ▲ 0.03 (0.27%)
KEL 8.05 Increased By ▲ 0.21 (2.68%)
KOSM 5.88 Increased By ▲ 0.15 (2.62%)
MLCF 90.52 Increased By ▲ 4.01 (4.64%)
NBP 190.17 Increased By ▲ 5.87 (3.19%)
PACE 11.53 Decreased By ▼ -0.12 (-1.03%)
PAEL 41.07 Increased By ▲ 1.11 (2.78%)
PIAHCLA 25.84 Increased By ▲ 0.17 (0.66%)
PIBTL 17.51 Increased By ▲ 0.24 (1.39%)
PPL 225.84 Increased By ▲ 3.17 (1.42%)
PRL 34.63 Increased By ▲ 0.17 (0.49%)
PTC 64.62 Increased By ▲ 0.88 (1.38%)
SEARL 91.38 Increased By ▲ 0.92 (1.02%)
SSGC 26.97 Increased By ▲ 0.30 (1.12%)
TELE 8.93 Increased By ▲ 0.02 (0.22%)
THCCL 69.16 Increased By ▲ 0.69 (1.01%)
TPLP 10.90 Decreased By ▼ -0.30 (-2.68%)
TREET 24.64 Decreased By ▼ -0.06 (-0.24%)
TRG 69.78 Decreased By ▼ -0.81 (-1.15%)
WAVES 11.16 Increased By ▲ 0.05 (0.45%)
WTL 1.27 No Change ▼ 0.00 (0%)
Pakistan

International court rules in favor of NTDC against Iranian co

The international arbitration court has ordered the Iranian company to pay Rs720 million in interest as compensatio
Published April 25, 2020 Updated April 25, 2020 05:39am
  • The international arbitration court has ordered the Iranian company to pay Rs720 million in interest as compensation for leaving a project unfinished in Pakistan.

The National Transmission and Dispatch Company Limited (NTDC) have won a major victory against an Iranian company in the international arbitration tribunal.

The international arbitration court has ordered the Iranian company to pay Rs720 million in interest as compensation for leaving a project unfinished in Pakistan.

The case between NTDC and the Iranian company was pending in the ICC International Arbitration Court in Paris. The Iranian company had abandoned the construction of the 500 KV Guddu Multan transmission line.

Following the termination of the contract by NTDC, a case was filed against the Iranian company in the international arbitration tribunal, on which the tribunal ruled in favor of NTDC, and the Iranian company was ordered to pay Rs720 million in interest as compensation.

The NTDC spokesperson said that winning the case against the Iranian company in the International Arbitration Court is a great victory of Pakistan. The Iranian company had left the work of 500 KV Guddu, Multan transmission line incomplete.

It may be mentioned here that NTDC is a company of the Government of Pakistan which deals with the transmission of electricity.

 