BR100 Decreased By (-0.02%)
BR30 Increased By (0.15%)
KSE100 Increased By (0.02%)
KSE30 Decreased By (-0.01%)
AGHA 7.36 Decreased By ▼ -0.20 (-2.65%)
BECO 5.10 Increased By ▲ 0.01 (0.2%)
BML 56.10 Increased By ▲ 1.12 (2.04%)
BOP 32.83 Decreased By ▼ -0.15 (-0.45%)
CNERGY 10.35 Increased By ▲ 0.25 (2.48%)
CSIL 5.07 Decreased By ▼ -0.06 (-1.17%)
FCCL 52.08 Increased By ▲ 0.83 (1.62%)
FFL 16.34 Increased By ▲ 0.16 (0.99%)
FNEL 1.21 Increased By ▲ 0.02 (1.68%)
KEL 7.18 Increased By ▲ 0.12 (1.7%)
KOSM 5.90 Increased By ▲ 0.36 (6.5%)
LOTCHEM 26.93 Decreased By ▼ -2.19 (-7.52%)
MLCF 89.50 Increased By ▲ 0.68 (0.77%)
NBP 194.99 Decreased By ▼ -2.50 (-1.27%)
NCPL 55.61 Increased By ▲ 0.59 (1.07%)
NPL 64.83 Decreased By ▼ -0.05 (-0.08%)
OGDC 312.40 Increased By ▲ 0.45 (0.14%)
PACE 10.28 Increased By ▲ 0.07 (0.69%)
PAEL 40.70 Decreased By ▼ -0.29 (-0.71%)
PIBTL 15.95 Decreased By ▼ -0.01 (-0.06%)
PPL 212.70 Increased By ▲ 0.04 (0.02%)
PRL 53.51 Increased By ▲ 0.97 (1.85%)
PTC 69.00 Decreased By ▼ -0.08 (-0.12%)
SSGC 24.85 Decreased By ▼ -0.25 (-1%)
TBL 9.52 Decreased By ▼ -0.10 (-1.04%)
TELE 8.35 Increased By ▲ 0.03 (0.36%)
TPL 18.15 Increased By ▲ 0.40 (2.25%)
TPLP 12.98 Decreased By ▼ -0.24 (-1.82%)
TREET 21.42 Decreased By ▼ -0.32 (-1.47%)
TRG 59.33 Increased By ▲ 2.44 (4.29%)

imageISLAMABAD: The Water and Power Development Authority (WAPDA) Chairman Zafar Mahmood has said that the first unit of the 969 MW-Neelum Jhelum Hydropower Project will be commissioned in June 2017 while three units will also come on line one by one by December 2017.

He expressed these views during his visit to the project, said a press release.

Expressing satisfaction over the pace of construction work, the Chairman observed that the progress on most of the components is ahead of revised schedule.

Appreciating the project authorities, the consultants and contractors for their efforts to expedite construction work, he directed them to work with the same level of commitment to complete the strategically important project during 2017.

The Chairman visited the dam site at Nauseri, river crossing at Majohi and power house at Chattar Klas to witness the construction activities going on there.

He also attended the break-through ceremony of the right tunnel in river cross section.

It is pertinent to mention that the two sections of the right tunnel-one excavated from dam site and the other from power house - were connected with amazing precision on January 9 against the target of January 15.

Performing the connectivity of the two sections, he said that Neelum Jhelum Project is a monument of the Pak-China friendship towards development of hydropower in Pakistan.

During the visit, the Chairman was briefed that overall progress on the project stands at 76 percent. Out of 68 kilometers long tunnels, 59 kilometers have so far been excavated, while the dam is 74 percent complete.

The power house and the switchyard of the project are scheduled to be completed in November this year. On its completion, Neelum Jhelum Hydropower Project will contribute 5.15 billion units of electricity every year to the National Grid.

Neelum Jhelum Hydropower Project Chief Executive Officer Lt. Gen. (R) Muhammad Zubair, Project Director Nayyar Ala-ud-Din and representatives of the consultants and contractors were also present on the occasion.

Copyright APP (Associated Press of Pakistan), 2016