National Transmission and Despatch Company Ltd (NTDC) has connected 1320 MW Sahiwal Coal Fired Power Plant with national grid through a 500 kV transmission line under China Pakistan Economic Corridor (CPEC) framework. Construction work of the 5 km long transmission line was completed in November 2016 ahead of its deadline. First unit of Sahiwal Coal Fired Power Plant is expected to start 660 MW power generation in May 2017 whereas power plant will be fully operational with 1320 MW in June 2017. The power will be evacuated through 500 kV grid station Yousafwala and 500 kV Grid Station Lahore.
The spokesman told that 500 kV transmission line Yousafwala-Lahore was closed for a week (20 to 27 January 2017) to connect the newly-built 1320 MW Sahiwal Coal Power plant with the national grid.