AIRLINK 74.29 Increased By ▲ 0.29 (0.39%)
BOP 4.95 Decreased By ▼ -0.07 (-1.39%)
CNERGY 4.37 Decreased By ▼ -0.05 (-1.13%)
DFML 38.80 Decreased By ▼ -0.40 (-1.02%)
DGKC 84.82 Decreased By ▼ -1.27 (-1.48%)
FCCL 21.21 Decreased By ▼ -0.44 (-2.03%)
FFBL 34.12 Increased By ▲ 0.11 (0.32%)
FFL 9.70 Decreased By ▼ -0.22 (-2.22%)
GGL 10.42 Decreased By ▼ -0.14 (-1.33%)
HBL 113.00 Decreased By ▼ -0.89 (-0.78%)
HUBC 136.20 Increased By ▲ 0.36 (0.27%)
HUMNL 11.90 No Change ▼ 0.00 (0%)
KEL 4.71 Decreased By ▼ -0.13 (-2.69%)
KOSM 4.44 Decreased By ▼ -0.09 (-1.99%)
MLCF 37.65 Decreased By ▼ -0.62 (-1.62%)
OGDC 136.20 Increased By ▲ 1.35 (1%)
PAEL 25.10 Decreased By ▼ -1.25 (-4.74%)
PIAA 19.24 Decreased By ▼ -1.56 (-7.5%)
PIBTL 6.71 Increased By ▲ 0.03 (0.45%)
PPL 122.10 Decreased By ▼ -0.90 (-0.73%)
PRL 26.65 Decreased By ▼ -0.04 (-0.15%)
PTC 13.93 Decreased By ▼ -0.40 (-2.79%)
SEARL 57.22 Decreased By ▼ -1.90 (-3.21%)
SNGP 67.60 Decreased By ▼ -1.90 (-2.73%)
SSGC 10.25 Decreased By ▼ -0.08 (-0.77%)
TELE 8.40 Decreased By ▼ -0.10 (-1.18%)
TPLP 11.13 Decreased By ▼ -0.10 (-0.89%)
TRG 62.81 Decreased By ▼ -2.04 (-3.15%)
UNITY 26.50 Increased By ▲ 0.25 (0.95%)
WTL 1.35 Increased By ▲ 0.01 (0.75%)
BR100 7,810 Decreased By -40.3 (-0.51%)
BR30 25,150 Decreased By -186.4 (-0.74%)
KSE100 74,957 Decreased By -250.1 (-0.33%)
KSE30 24,083 Decreased By -59.5 (-0.25%)

imageBAHAWALNAGAR: Minister of State for Water and Power Abid Sher Ali has assured cricket fans that there would be no load shedding across the country on the day of Pakistan Super League (PSL) final, on March 5 (Sunday) in Lahore.

The minister made this announcement after inaugurating the 220 KV grid station at Chishtian near Bahawalnagar.

Ali reiterated that the government was committed to eliminate load shedding from the country. Power projects of over 10,000 MW capacity are being completed on fast track basis, added the minister.

The 220 KV grid station Chishtian along with 88 km transmission line has been constructed by National Transmission and Dispatch Company Ltd. (NTDC) with the cost of Rs 2.633 billion.

He appreciated the NTDC Management, engineers and staff for timely completion of the project and said that the grid station will end forced load shedding, improve voltage level and minimize trippings which was being faced due to overloading of the system.

Copyright Business Recorder, 2017

Comments

Comments are closed.