AIRLINK 78.39 Increased By ▲ 5.39 (7.38%)
BOP 5.34 Decreased By ▼ -0.01 (-0.19%)
CNERGY 4.33 Increased By ▲ 0.02 (0.46%)
DFML 30.87 Increased By ▲ 2.32 (8.13%)
DGKC 78.51 Increased By ▲ 4.22 (5.68%)
FCCL 20.58 Increased By ▲ 0.23 (1.13%)
FFBL 32.30 Increased By ▲ 1.40 (4.53%)
FFL 10.22 Increased By ▲ 0.16 (1.59%)
GGL 10.29 Decreased By ▼ -0.10 (-0.96%)
HBL 118.50 Increased By ▲ 2.53 (2.18%)
HUBC 135.10 Increased By ▲ 2.90 (2.19%)
HUMNL 6.87 Increased By ▲ 0.19 (2.84%)
KEL 4.17 Increased By ▲ 0.14 (3.47%)
KOSM 4.73 Increased By ▲ 0.13 (2.83%)
MLCF 38.67 Increased By ▲ 0.13 (0.34%)
OGDC 134.85 Increased By ▲ 1.00 (0.75%)
PAEL 23.40 Decreased By ▼ -0.43 (-1.8%)
PIAA 26.64 Decreased By ▼ -0.49 (-1.81%)
PIBTL 7.02 Increased By ▲ 0.26 (3.85%)
PPL 113.45 Increased By ▲ 0.65 (0.58%)
PRL 27.73 Decreased By ▼ -0.43 (-1.53%)
PTC 14.60 Decreased By ▼ -0.29 (-1.95%)
SEARL 56.50 Increased By ▲ 0.08 (0.14%)
SNGP 66.30 Increased By ▲ 0.50 (0.76%)
SSGC 10.94 Decreased By ▼ -0.07 (-0.64%)
TELE 9.15 Increased By ▲ 0.13 (1.44%)
TPLP 11.67 Decreased By ▼ -0.23 (-1.93%)
TRG 71.43 Increased By ▲ 2.33 (3.37%)
UNITY 24.51 Increased By ▲ 0.80 (3.37%)
WTL 1.33 No Change ▼ 0.00 (0%)
BR100 7,493 Increased By 58.6 (0.79%)
BR30 24,558 Increased By 338.4 (1.4%)
KSE100 72,052 Increased By 692.5 (0.97%)
KSE30 23,808 Increased By 241 (1.02%)

imageISLAMABAD: Around 75 per cent work has already been completed on 425-525 MW Nandi Pur Power project and its first unit will start generating 95 MW by May.

This was stated by Chief Engineer Nandi Pur Power Project Shahid Sohail while talking to APP here Monday.

He said that the 425-525 MW Nandi Pur Power plant would be fully operationalised by December and vigorously work was being carried out to complete the project in due time.

He said that the project was being set up at left bank of Upper Chenab Canal (within the premises of the existing small (Hydel Power Station, Nandipur, Gujranwala).

The Nandi Pur Power Project would cost Rs56 billion, he added. Sharing the details of the project, he said that the plant would generate 425MW if run with furnace oil and 525MW with gas.

He said that the Economic Coordination Committee (ECC) had approved the project in December 2007 and its schedule time completion was 2011. However, the project was delayed and now would complete in December.